In a scathing 15-page judgment delivered on 28 November 2025, the Maharashtra Real Estate Appellate Tribunal has dismissed yet another appeal filed by Sanvo Resorts Pvt. Ltd. (developer of Marathon Nexzone, Panvel) and used unusually strong language to describe the root cause of the project’s eight-year delay: the promoter’s own “greed” to construct and sell extra floors beyond what was originally sanctioned.

The Case in Brief

Flat No. 2203 on the 22nd floor of Atlas-1 (Building S2 B-Wing) was booked in 2014 for ₹59.72 lakh. The registered Agreement for Sale executed in March 2016 promised possession by 31 December 2017. The buyers — Mr. & Mrs. Bharat More — have paid ₹47.61 lakh (over 80% of the cost) but are still waiting for possession. Frustrated, they filed a complaint before MahaRERA seeking delayed-possession interest under Section 18 of the RERA Act.

On 18 May 2021, MahaRERA ordered Marathon to pay interest from 1 October 2018 till the date of part Occupation Certificate, while granting the promoter the benefit of the COVID-19 moratorium period. Marathon challenged this order before the Appellate Tribunal.

Tribunal’s Damning Observation on “Greed”

The bench of Shri Shriram R. Jagtap (Judicial Member) and Shri Rajagopal Devara (Administrative Member) rejected every ground raised by the promoter and held (para 17):

“We are of the view that had the promoter adhered to the sanctioned plan/commencement certificate dated 20.10.2012 issued by the Collector Raigad [which allowed only 27 floors] the building would have been completed in time. However, because of greed of promoter to construct more floors above 27th floors resulted in submitting revised plans before several Authorities for approvals at belated stage.”

The Tribunal noted that the original sanction in 2012 was for 27 floors, but Marathon kept applying for 29–33 habitable floors, causing repeated delays in approvals from CIDCO-NAINA, AAI, NHAI and others — all self-created.

Delay in Approvals Is Normal, Not Force Majeure

Relying on the Supreme Court’s ruling in DLF Home Developers Ltd. vs Capital Greens Flat Buyers Association (2020), the Tribunal reiterated:

“A delay in the approval of building plans is a normal incident of a construction project… a developer… cannot set this up as a defence to a claim for compensation.”

The bench also cited Imperia Structures (2020) and Newtech Promoters (2021) to underline that the allottee’s right to interest under Section 18 is “unqualified and absolute” once possession is delayed, irrespective of the promoter’s excuses.

Eighth Straight Loss for Marathon Nexzone at Appellate Level

This is the eighth consecutive Marathon Nexzone appeal dismissed by the Tribunal in identical circumstances. Earlier dismissed appeals include those of Shreedhar Singh, Sushil Salvi, Shital Deshmukh, Neha Bagwe and others — all cited in the present order.

What It Means for 2,000+ Remaining Buyers

With this judgment, the legal position is now cast in stone:

  • Marathon cannot plead force majeure for delays caused by its own decision to add extra floors.
  • Every buyer who has not yet received possession or full interest is entitled to claim Section 18 interest from the due date (minus only the COVID moratorium period).
  • Execution proceedings can now be filed confidently before MahaRERA for recovery.

Marathon Nexzone, once marketed as a premium township on the Mumbai-Pune highway, continues to remain partially occupied even eight years after the first promised possession dates.

Also Read: MahaRERA Orders Refund for Homebuyer in Godrej Greens Dispute: A Win Against Excessive Forfeiture

You May Also Like

Mumbai’s Open Spaces Row: MLA Ameet Satam Asks BMC to Scrap Interim Policy

MLA Ameet Satam has urged the BMC to scrap its interim open spaces policy, warning against misuse by private parties. He wants BMC to directly maintain parks and gardens, with regulated ads funding their upkeep.

PMRDA Launches Mega E-Auction: Prime Shivajinagar Commercial Plot of 71,400 Sqm Hits Record Base Price of Rs 902 Crore

The Pune Metropolitan Region Development Authority (PMRDA) has launched an e-auction for 30 plots, highlighted by a prime 71,400 sqm commercial site in Bhamburda (Shivajinagar) at a historic base price of Rs 902 crore. Registration opens December 15, 2025, with live bidding on January 23, 2026, promising a boost to Pune’s urban development.

Mumbai Among World’s Top Prime Housing Markets, Ranks 6th Globally

Mumbai has emerged as one of the world’s hottest luxury housing markets, ranking 6th globally in Knight Frank’s latest Prime Global Cities Index Q2 2025. With 8.7% annual growth in prime property prices, the city is riding on infrastructure upgrades and strong wealth-driven demand, placing India firmly on the global luxury real estate map alongside Bengaluru and Delhi.

India’s Housing Market Shines Globally: 9.6% Price Growth in 2025 Outpaces World Average

India’s residential market outperforms global peers with 9.6% YoY price growth in Q3 2025 — ranking 10th worldwide and the only APAC entry in top 10; NCR surges 19%, sales hit 348,000+ units — Knight Frank report highlights resilient end-user demand amid global 2.4% average.