What happens to a homebuyer if the builder is terminated by the authority under whom the project is. A similar case popped up, when a homebuyer approached MahaRERA for help, and found out that the builder was terminated by SRA.

By Varun Singh

In an interesting case, a homebuyer recently approached MahaRERA, seeking relief.

The relief was sought by homebuyer Shilpa More against builder Ashok Gupta

The homebuyer claimed that builder should refund her money with interest and compensation for failing to execute agreement and handing over the possession of the flat that she had booked.

More via a reservation letter had booked an apartment in the builder’s Ganeshwadi CHS-SRA, at Ghatkopar, she even had paid some money tot he builder.

Also Read: Builder cancels booking, MahaRERA orders refund

The builder meanwhile, informed MahaERA that the SRA has terminated him as the promoter of the project. He also claimed to have filed an appeal against the termination.

Gautam Chaterjee, Chairman, MahaRERA in his order noted, that the right of complainant as allottee in the project shall continue to be protected even after change of promoters.

Chaterjee aslo restrained the builder from creating any new allottee in the project till further orders.

He even advised the complainant homebuyer to become an intervener in the current pending litigation before SRA, or any other forum or Court.

The homebuyer’s right in the project was protected under section 15 of RER Act. This section talks about obligation of builder in case of transfer of a real estate project to a third party.

Also Read: Action Against 20 Projects By MahaRERA In A Day.

Leave a Reply
You May Also Like

Mumbai’s Prime Properties Among 40 Enemy Assets to Be Auctioned on February 13, 2025

The Government of India has announced the e-auction of 40 enemy properties, including high-value real estate in Mumbai’s Colaba, under the Enemy Property Act, 1968. The auction, scheduled for February 13, 2025, will be conducted through MSTC India Ltd. Investors and buyers can participate in the online auction, with properties spanning multiple states, including Maharashtra, Tamil Nadu, West Bengal, and Uttar Pradesh.

Ever Wonder Where Your Selfies Go? Inside the Giant “Digital Warehouses” Booming in India

A massive construction boom for data centers—the ‘digital warehouses’ that power our online world—is underway, fueled by the explosive growth of Artificial Intelligence. A recent report reveals a staggering $180 billion is being poured into these facilities across Asia. Mumbai is at the heart of this transformation, with huge new AI-ready campuses and a major push for green energy.

🏗️ Realty Stocks Open Flat to Mild Gains; Large Caps Show Early Strength, Mid-Caps Mixed

Realty stocks opened flat to mildly positive today, with large developers steady and mid-caps mixed. The sector is expected to trade range-bound with selective opportunities through the day.

MahaRERA Orders Kolte-Patil Developers to Pay Interest for Delayed Possession in Vile Parle Redevelopment Project

MahaRERA has partly allowed a complaint by Manohar Shetty and Lalita M. Shetty against Kolte-Patil Developers, ordering payment of interest at SBI’s highest MCLR + 2% for the delay in handing over possession of a flat in the Jai Vijay redevelopment project from October 2019 to March 2020. The ruling underscores that contractual possession dates bind promoters despite project extensions or external delays.