MahaRERA has raised serious concerns over 212 housing projects launched January 2023 onwards

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has raised concerns on 212 housing projects spread across the state. These projects were launched between January and April 2023 and since no information on their construction status has been provided to the housing regulator, thereby making them doubtful.

After registering a project with MahaRERA, it is mandatory to submit Quarterly Progress Report (QPR) in a prescribed format on the regulator’s website. Therefore, it is evident that these developers are not taking their projects and regulations seriously, as required.

This negligence in fulfilling compliance and commitments towards homebuyers poses a significant risk. Therefore, to caution people, and save them from risking their life long savings, MahaRERA has published a district-wise list of such projects on its website. Among these, Pune has the maximum number of projects at 47.

Following Pune are Nashik and Palghar to have 23 projects each. Thane has 19 such housing projects, Raigad with 17, Sambhaji Nagar has 13 and Nagpur with 8 projects.

According to statistics, Mumbai Metropolitan Region and Konkan have the highest number at 76, followed by Pune at 64, North Maharashtra with 31, Vidarbha with 21 and Marathwada with 20. In addition to Section 11 Regulation Rules 3, 4 and 5 of the Real Estate (Regulation and Development) Act, as per Section 3 and 4 of Order No 33/2022 dated July 5, 2022, every developer is required to submit the prescribed statement forms quarterly/ annually to MahaRERA and update them on the website.

This helps in closely monitoring of construction, expenses and related aspects. It also helps in identifying discrepancies, if any, and allows homebuyers to access the required project related information they have invested in or want to invest in. Out of 2,369 projects registered with MahaRERA between January and April 2023, 886 of them had not submitted Quarterly Progress Reports.

Consequently, notices were issued under Section 7, providing them with a 30 days window for rectification. Section 7 allows the regulator to suspend the project and freeze the project’s bank account, banning all transactions. Thereafter, reminders were also sent to them. Later, penalty was levied on 672 projects, 244 of whom failed to update Quarterly Progress Reports despite payment of penalties.

Attempts are underway to get them to update the project’s status. Of the total defaulters, 60 projects were registered in January 2023, 58 in February 2023, 40 in March 2023 and 56 in April 2023, thus, a total of 212 projects have not responded to all the communications of MahaRERA.

Hence, due to their indifferent approach, MahaRERA has finally made their names public to caution homebuyers and safeguard their interests.

DISTRICT-WISE DETAILS OF 212 PROJECTS (JANUARY-APRIL 2023)

Mumbai Metropolitan Region with Konkan
Palghar- 23,
Thane- 19,
Raigad- 17,
Mumbai City- 7,
Mumbai Suburban- 4,
Ratnagiri- 5,
Sindhudurg- 1
Total- 76

Pune Region
Pune- 47,
Sangli- 6,
Satara- 5,
Kolhapur- 4,
Solapur- 2
Total- 64

North Maharashtra
Nashik- 23,
Ahmednagar- 5,
Jalgaon- 3
Total- 31

Vidarbha
Nagpur- 8,
Amravati- 4,
Chandrapur- 3,
Wardha- 3,
Bhandara- 1,
Buldana- 1,
Akola- 1
Total-21

Marathwada
Sambhaji Nagar- 13,
Beed- 3,
Nanded- 2,
Latur- 1,
Jalna- 1
Total- 20

Also Read: MAHARERA PROPOSES THREE BANK ACCOUNT SYSTEM TO SAFEGUARD HOME BUYERS’ INTERESTS

You May Also Like

PMAY-U 2.0: New Rules Cap Built-Up Area, Protect EWS Homebuyers from Overpricing

New PMAY-U 2.0 rules cap EWS built-up area, mandate beneficiary registration and NOCs to protect homebuyers from overpricing.

🏘️ Realty Stocks Close Flat After a Quiet Session; Large Developers Stay Resilient Amid Mid-Cap Weakness

Realty stocks ended the day flat, with the Nifty Realty Index barely lower. Large developers provided stability, while mid-caps underperformed amid muted participation. The sector remains in a consolidation phase ahead of key data.

Bought a House After Selling One? This Brokerage Mistake Won’t Save on Capital Gains Tax

If you sell a house in Mumbai and buy another to save…

17,000 Lives, 31 Hectares, 1 Landmark Project: Mata Ramabai Ambedkar Nagar Redevelopment Kicks Off Today

In a historic step for Mumbai’s redevelopment, work on the Mata Ramabai Ambedkar Nagar project in Ghatkopar begins today. Spanning 31.82 hectares and impacting 17,000 residents, this landmark initiative will deliver free 1 BHK homes, modern infrastructure, and commercial spaces — transforming one of Mumbai’s oldest slum clusters into a model urban community.