Authority orders refund after deducting only 1.5% of unit cost, directs interest from September 13, 2024.

In a significant ruling that strengthens homebuyer rights, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has held that developers cannot forfeit the entire booking amount when an allottee cancels a unit booking. The Authority directed Mahalunge Township Developers LLP (Godrej Hill Retreat 2) to refund the full amount paid by complainant Bhuvan Chawla, after deducting only 1.5% of the total unit cost, as permitted under Order No. 60/2024 dated 03.09.2024.

The order was pronounced by MahaRERA Chairperson Shri Manoj Saunik on November 20, 2025, after the matter was reserved for orders on August 26, 2025.


Case Background

The complainant, homebuyer Bhuvan Chawla, booked Unit No. 2504 (25th floor) in Godrej Hill Retreat 2, paying ₹8,49,442 between May and June 2024. An allotment letter was issued on June 22, 2024, showing the proposed possession date as March 28, 2027, with a total unit cost of ₹80,89,925.42.

However, after receiving the draft Agreement for Sale on July 2, 2024, Chawla raised objections to multiple clauses that he alleged were unilateral, arbitrary and contrary to Section 14(2) of RERA, including:

  • Provisions permitting the developer to change building plans unilaterally
  • Escalation charges
  • Excessive holding/maintenance costs

Chawla requested cancellation and refund on July 29, 2024, within 37 days of the allotment letter—within the permissible period defined in the model allotment form under Order 60.


Developer Forfeited Entire Amount

Instead of processing a refund, the developer forfeited the full booking amount, claiming the cancellation was buyer-driven and arguing that forfeiture was justified under contract law. The respondent relied on Supreme Court judgments regarding earnest money to support its position.

The complainant issued repeated follow-ups and served a legal notice on December 26, 2024, receiving a reply on February 3, 2025, after which he filed the present complaint on February 14, 2025.


MahaRERA Examination

MahaRERA observed:

  • The allotment letter was signed only by the promoter; yet both parties accepted it as valid.
  • The developer accepted more than 10% consideration without executing an Agreement for Sale, prima facie violating Section 13(1) of RERA.
  • Under Clause 9 of the model allotment form, when cancellation is requested between 31–60 days, the developer may deduct only 1.5% of the unit cost.
  • Refund must be made within 45 days from the cancellation request.
  • Delay mandates payment of interest at SBI highest MCLR + 2%.

Key Findings & Order

MahaRERA held that the developer’s action was inconsistent with RERA norms:

“The action of the respondent in forfeiting the entire paid amount of Rs. 8,49,442/- is inconsistent with Clause 9 of the allotment letter and the provisions of Order No. 60/2024.”

Final Directions

  • Developer must refund the balance amount after deducting only 1.5% of total unit cost
  • Refund must be paid within 60 days
  • Interest due from September 13, 2024, until realization, at rate prescribed under Rule 18
  • Refund includes only principal consideration, excluding stamp duty, taxes, registration fees and statutory charges
  • No costs were awarded

Key Legal Significance

This ruling reinforces that:

  • Developers cannot arbitrarily confiscate booking amounts
  • Refund rules are governed uniformly by Order No. 60/2024 and model allotment terms
  • Buyer intent or cancellation reasons are irrelevant once procedure is followed
  • MahaRERA prioritizes consumer protection and transparency obligations

Industry professionals expect this decision to influence how forfeiture disputes are handled across Maharashtra.

Also Read: How Much Money Can a Builder Forfeit If a Homebuyer Cancels a Deal?

You May Also Like

🏗️ Realty Stocks Stay Resilient as Markets Open; RBI’s Steady Repo Rate Lends Support to the Sector

Real estate stocks opened steady and held ground after the RBI kept the repo rate unchanged at 5.25%, reinforcing stability for homebuyers and developers alike.

Akshay Kumar Sells Mumbai Apartment for Rs. 4.35 Crore, Earns 84% Profit Over Seven Years

Bollywood star Akshay Kumar has sold his apartment in Oberoi Sky City, Borivali East, for Rs. 4.35 crore. The 1,073 sq. ft. unit, purchased in 2017 for Rs. 2.37 crore, saw an 84% appreciation in value. This marks his second recent sale in the same building, following a Rs. 4.25 crore transaction in January 2025.

Builders to provide opportunity to Agniveers

Builders Association of India (BAI) Supports Agneepath Scheme. Agniveers to be provided…

Godrej Properties enters Golf Course Road Extension in Gurugram

Godrej Properties enters Golf Course Road Extension in Gurugram, Haryana. The project…