MahaRERA Order Overturned: Homebuyers Win Delay Interest from CCI Projects in Rivali Park’s Winter Green Project

In a major win for homebuyers, the Maharashtra Real Estate Appellate Tribunal has directed CCI Projects to pay delay interest at SBI MCLR + 2% to two allottees in the Rivali Park Winter Green project, setting aside the MahaRERA order that had rejected their compensation claim. The Tribunal ruled that unilateral extensions of possession dates by the promoter are invalid and that buyers do not waive their rights by continuing payments.

Individual Agreement Possession Dates Prevail Over Extended RERA Project Timelines for Calculating Delay Interest

A December 2025 MahaRERA order rules that possession dates in individual Agreements for Sale prevail over extended project timelines on the portal, entitling buyers to delay interest under Section 18—even rejecting builders’ COVID-19 extension claims for contracts signed post-pandemic.