MahaRERA Rejects Builder’s Plea to Sell Flat Before Refunding Buyer

MahaRERA has ruled that builders cannot make refunds conditional upon resale of flats. In the Viva Vishnupuram case, the Authority ordered a full refund with interest after finding a decade-long delay in handing over possession, reinforcing the unconditional rights of homebuyers under Section 18 of RERA.

MahaRERA Orders Interest for Delay in Gulraj Trinity Project, Allows 15 Homebuyer Complaints

MahaRERA has ordered Reliable Builders & Developers to pay interest for delayed possession to 15 homebuyers in the Gulraj Trinity project, holding that contractual possession dates cannot be overridden by unilateral extensions.

Booking Form Alone Does Not Create Binding Sale Contract: MahaRERA Orders Refund to Homebuyer

MahaRERA has ruled that a booking application form does not by itself create a binding sale contract and directed Mahindra Happinest Developers to refund ₹1.50 lakh to a homebuyer, holding that forfeiture was illegal as the booking was never completed.

“Fit-Out Possession” Declared Legally Invalid Without OC: MahaRERA Rules in Favor of Delayed Homebuyers

In a landmark MahaRERA ruling, “fit-out possession” without OC is deemed legally invalid, holding promoters liable for delays in a Vasai housing project. Homebuyers awarded interest from Dec 2018, deferred till OC, highlighting RERA’s balance between buyer relief and project viability.

MahaRERA Orders Refund for Homebuyer in Godrej Greens Dispute: A Win Against Excessive Forfeiture

MahaRERA has ruled in favor of homebuyer Chetan Kaushal, ordering Dreamworld Landmarks LLP to refund ₹5.42 lakh (minus 2% forfeiture) for his cancelled Godrej Greens flat in Pune. A win for buyer rights in 2025!