MahaRERA Orders Kolte-Patil Developers to Pay Interest for Delayed Possession in Vile Parle Redevelopment Project

MahaRERA has partly allowed a complaint by Manohar Shetty and Lalita M. Shetty against Kolte-Patil Developers, ordering payment of interest at SBI’s highest MCLR + 2% for the delay in handing over possession of a flat in the Jai Vijay redevelopment project from October 2019 to March 2020. The ruling underscores that contractual possession dates bind promoters despite project extensions or external delays.

Homebuyers Entitled to Interest on Refund from Date of Payment Receipt, Not Project Default Date – Landmark Win in Withdrawal Case

In a key February 2026 decision, MahaREAT ruled that homebuyers withdrawing from delayed projects under RERA are entitled to interest from the promoter’s receipt of payments—not from later default dates—overturning a MahaRERA order in the Mullaji vs. Onyx Builders case involving stalled projects in Kurla West, Mumbai.