Homebuyers facing endless project delays, take note: A recent MahaRERA order dated February 3, 2026, delivers a powerful victory for a Vasai flat owner who waited over 12 years. The Authority ordered the builder to hand over the flat immediately (with full Occupancy Certificate) and pay hefty interest on nearly ₹20 lakh from late 2013 onward—at SBI’s highest MCLR + 2% (currently around 10.8% p.a.). Crucially, the ruling shuts down the common builder tactic: “We offered refund years ago—you chose to wait, so no compensation!”

This case sends a clear signal: RERA’s protections for delayed possession are strong, even in old pre-RERA agreements, and past refund proposals don’t wipe out your rights if you hold on for the flat.

Buyer’s Ordeal: ₹20 Lakh Paid in 2010–Still No Flat in 2026

Vilas Janardan Gode booked a 410 sq ft carpet area flat in “Veena Velocity Phase II” (MahaRERA Reg. P99000014147), Vasai, in October 2010 for ₹19.68 lakh.

  • He paid almost the full amount: ~₹19.60 lakh directly (₹14.97 lakh via IDBI Bank home loan) (total ~99.5% towards consideration).
  • Extras included stamp duty, service tax/GST, and over ₹8 lakh in loan interest by 2019.
  • Agreement registered November/December 2010—but no possession date was specified.
  • Builder verbally promised ~1-year delivery, but reality was very different.

Construction halted for years due to a 2011 court injunction in a land dispute (settled only in 2017). Work resumed, completed by November 2018, but no OC from CIDCO/Vasai—blamed on landowner insolvency/legal hurdles. OC finally issued February 13, 2025.

The buyer filed his complaint in September 2020, demanding possession, interest for delay (from 2013 or project proposed date 2017), and ₹5 lakh compensation.

Builder’s Main Defences: Court Stay, Refund Offers, and “No Date Promised”

The developer (M/s. Nikunj Developers) argued:

  • No fixed possession date in the 2010 agreement (under old MOFA law), so no breach.
  • Delay caused by unavoidable court stay (2011–2017) + later OC technical issues.
  • Multiple refund offers with interest (9–12% p.a.) in 2013, 2014, and 2015—buyer refused, so he “waived” claims.
  • RERA doesn’t fully apply to pre-2016 sales; project extensions (to 2020) cover them.
  • Most other buyers took “fit-out” (semi-finished) possession; only this buyer insisted on full OC.

MahaRERA’s Firm Ruling: Delay Interest Is Your Unqualified Right

Member Ravindra Deshpande rejected key defences:

  • RERA applies retroactively to ongoing/incomplete projects (per Supreme Court in Newtech Homes).
  • No date in agreement? Reasonable possession time is 3 years from agreement date (Supreme Court in Fortune Infrastructure)—so due by November 2013.
  • Court stay/OC delays don’t excuse indefinite wait after buyer paid nearly full amount.
  • Section 18 gives unqualified right to interest if buyer stays in project (not withdrawing for refund).
  • Rejecting old refund offers ≠ waiver; buyer chose the flat, so interest applies.
  • Interest is compensatory—no extra ₹5 lakh needed.

Final Directions (3 Feb 2026):

  • Hand over full possession with OC within 30 days.
  • Pay interest on ₹19,59,758 (consideration paid, excluding stamp duty/taxes/GST) at SBI highest MCLR + 2% p.a. (currently 8.80% + 2% = 10.80% p.a. as of Feb 2026).
  • From 27 November 2013 till actual possession (potential payout: several lakhs—exact calc pending).
  • ₹10,000 case costs to buyer.

Key Takeaways for Every Homebuyer in Maharashtra

  • RERA trumps old agreements and project extensions for individual delay claims.
  • 3-year rule often sets the clock for interest if no date specified.
  • Builders’ “we offered refund earlier” defence fails if you stick with the project.
  • Interest accrues monthly on what you paid toward the flat price—powerful compensation.
  • If delayed beyond reasonable time, check your project’s RERA portal and file under Section 18 early.

This ruling reinforces that homebuyers aren’t powerless against years-long waits. If you’re in a similar boat, your rights are real—and enforceable.

Also Read: Landmark MahaRERA Tribunal Ruling: Homebuyers Can Claim Interest on Delay Even After Taking Possession

You May Also Like

Housing Sales Scale New Peak in 2022

Housing Sales in Top 7 Cities Scale New Peak in 2022, Breach…

ALL IN THE NAME OF POOR! The Detrimental Impact of DCR 33(11)

It’s a matter of great concern for all Mumbaites that successive governments have shown little interest in resolving the burning issue of housing, including the recent phenomenon of private property redevelopment. This article exposes how new DC regulations, particularly DCR 33(11), are ironically worsening the city’s housing crisis in the name of the poor.

86% Projects Launched Post RERA in H2 2017 and 2018 Completed in Top 7 Cities

Chennai sees highest 90% completions of projects launched in this period, followed…

Home sold in Worli for ₹151 Crore

A home spread over two floors in a luxury realty project was…