In a landmark judgment that reinforces the supremacy of the Real Estate (Regulation and Development) Act (RERA), the Maharashtra Real Estate Appellate Tribunal has struck down a promoter’s attempt to use an “automatic extension” clause to avoid liability for a six-year delay in possession. The Tribunal ruled that such contractual terms cannot override the statutory protections afforded to homebuyers under RERA.

The Case of Fali Erach Poncha vs. Theme Infraprojects

The dispute centered on Flat No. 702 in Building A-I of the project “Signature Residency” (MahaRERA Reg. No. P51700008025), located in Thane. The appellant, Mr. Fali Erach Poncha, had purchased the flat from Theme Infraprojects Private Limited (the Respondent) via an agreement dated March 27, 2014.

Mr. Poncha had paid the entire consideration of ₹62,00,000 by June 2013. According to the agreement, the builder was supposed to hand over possession on or before March 2017. However, the project remained incomplete years after the deadline.

The Builder’s “Automatic Extension” Trap

When the homebuyer sought a refund due to the delay, the promoter pointed to Clause 12 of their agreement. This clause claimed the promoter was entitled to an “automatic extension” of time if construction was stalled due to reasons like:

  • Non-availability of building materials (steel, sand, cement).
  • Delay in government approvals or utility connections.
  • Court orders or changes in statutory rules.

The builder argued that since the homebuyer had signed the agreement, they had “consented” to wait indefinitely for these reasons. They also cited the COVID-19 pandemic and various court stay orders as force majeure (acts of God).

Tribunal Strikes Down One-Sided Clauses

The Appellate Tribunal, comprising Justice S. S. Shinde and Shrikant M. Deshpande, rejected these arguments. The Tribunal’s reasoning provides a vital shield for all homebuyers:

  1. RERA Overrides Contracts: The Tribunal noted that RERA is retroactive and applies to all ongoing projects. Contractual terms that contradict the spirit of the Act cannot be used to deprive a consumer of their rights.
  2. Strict Definition of Force Majeure: The Tribunal clarified that under Section 6 of RERA, force majeure only includes natural calamities like floods, cyclones, or war. Delays in obtaining NOCs or materials do not count as “acts of God”.
  3. Timeline Matters: The builder tried to blame a 2017 High Court stay and the 2020 pandemic for the delay. The Tribunal pointed out that the possession date (March 2017) had already passed before these events occurred, meaning the builder was already in default.
  4. No “Indefinite” Waiting: The judgment stated that merely signing an agreement does not mean a buyer has consented to wait forever for a home.

The Rescue: Refund and Interest Ordered

The Tribunal set aside an earlier MahaRERA order that had allowed the builder to delay the refund until the project’s completion. It ruled that Section 18 of RERA gives a homebuyer an unqualified right to a refund “on demand” if the builder fails to give possession on time.

The promoter was directed to:

  • Refund the entire principal amount of ₹62,00,000.
  • Pay interest at the rate of SBI MCLR + 2% from the date of payment until realization.
  • Execute a Deed of Cancellation and assist the buyer in getting a refund for stamp duty and registration charges from government authorities.

Also Read: MahaRERA Appellate Tribunal Orders Developer to Refund Buyers, Rejects Cancellation Fee

You May Also Like

Ahmedabad Emerges as India’s Rising Business Hub with Robust Office Demand and 25.5% Rent Upside

Ahmedabad’s office market has entered a landlord-favorable phase, with a 25.5% premium in market rent over passing rent. A new report by CREDAI and a real estate research firm shows BFSI and tech firms are driving demand, while GIFT City is emerging as the growth engine of Gujarat’s commercial real estate.

Pune’s Property Market Soars: 23% YoY Hike in Registrations Fuels State Coffers

Pune’s real estate market experienced a significant boom in September 2025 with property registrations climbing 23% YoY, contributing INR 523 crore in stamp duty. The city logged its highest property registrations for the first nine months of the year in the last four years, driven by sustained demand for homes under INR 1 Cr and a growing preference for larger units.

Monetary Policy Reaction – Entering the Red Zone

By Anuj Puri, Chairman – ANAROCK As anticipated, with inflation edging higher in…

MahaRERA Limits Tenure of SRO Representatives, Sets Expertise Requirement

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has capped the tenure of Self-Regulatory Organisation (SRO) representatives at two years. It also mandates that representatives assisting with housing project registrations must be experts in legal, financial, or technical domains. This move aims to enhance the efficiency and transparency of the registration process while avoiding conflicts of interest.