In one of the strongest regulatory actions in recent times, the Maharashtra Real Estate Regulatory Authority has issued show cause notices to 8,212 housing projects across Maharashtra for failing to submit mandatory Quarterly Progress Reports (QPRs).
The move sends a clear warning to developers: comply or face cancellation, financial penalties, and operational restrictions.
📊 Massive Non-Compliance Across the State
Out of 33,029 ongoing housing projects, a staggering 8,212 projects failed to update their QPRs for the January–March quarter by the April 20 deadline.
📍 Region-wise Breakdown:
- Mumbai Metropolitan Region & Konkan: 4,644 projects
- Pune Region: 2,311 projects
- Khandesh: 511 projects
- Vidarbha: 483 projects
- Marathwada: 238 projects
The highest concentration of non-compliance comes from:
- Thane (1,475 projects)
- Mumbai Suburban (1,263 projects)
- Pune district (1,957 projects)
⚖️ What Is the Violation?
Under the Real Estate (Regulation and Development) Act, 2016, developers must update project details every quarter through:
- Form 1: Engineer certification
- Form 2: Architect certification
- Form 3: CA certification
These reports include:
- Project progress
- Funds received and spent
- Inventory sold (flats, garages)
- Changes in approved plans
👉 This data is critical for homebuyer transparency.
🚫 Strict Action Looming
MahaRERA has given developers 60 days to respond and comply.
If they fail, authorities may take severe action:
- ❌ Project registration cancellation or suspension
- 💰 Penalty of ₹50,000
- 🏦 Freezing of project bank accounts
- 📢 Ban on advertising and marketing
- 📝 Restriction on property registrations
This effectively means projects could come to a standstill, directly impacting both developers and homebuyers.
🏦 Why QPR Compliance Is Critical
Under RERA rules:
- 70% of buyer funds must be deposited in a dedicated project account
- Withdrawals require certified progress reports (Forms 1, 2, 3)
Failure to update QPRs raises serious concerns:
👉 Is the money being used correctly?
👉 Is construction progressing as claimed?
🗣️ Chairman’s Strong Warning
Manoj Saunik, Chairman of MahaRERA, made the authority’s stance crystal clear:
“MahaRERA has always been striving to protect homebuyers’ interest and ensure he or she does not get cheated in any manner. From the initiation of the project till its completion, all the information available to the developer should also be available to the homebuyer.”
He further added:
“If any developer does not update the quarterly progress report despite repeated follow-ups, MahaRERA will not hesitate to cancel or keep such project’s registration in abeyance.”
⚠️ What This Means for Homebuyers
This crackdown is a double-edged sword:
👍 Positive:
- Greater transparency
- Stronger enforcement
- Protection against fund misuse
⚠️ Risk:
- Project delays if registrations are suspended
- Temporary halt in transactions
- Financial stress on already delayed projects
🎯 The Big Message
This action signals a zero-tolerance approach toward non-compliance.
👉 For developers: Compliance is no longer optional
👉 For homebuyers: Track your project’s QPR status on MahaRERA portal
Because in today’s regulated market:
No updates = No trust = No business