MahaRERA Orders Refund With Interest as Homebuyers Win Long-Running Delay Battle

In a significant ruling reinforcing homebuyer protections under the Real Estate (Regulation and Development) Act, 2016, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has categorically held that uploading Form 4 (Architect’s Certificate) does not amount to legal project completion in the absence of an Occupation Certificate (OC).

The Authority passed the order while deciding a batch of complaints filed by homebuyers in the “Kuber Ganraj” project (MahaRERA Registration No. P51700008998), developed by promoter Ashvinkumar Dahyabhai Patel. The ruling resulted in refunds with interest being granted to three allottees after years of delay.


Form 4 Uploaded, But Project Still Without OC

As recorded by MahaRERA, the project was originally scheduled for completion in 2018, with a revised completion date of 2019. However, the project never obtained an Occupation Certificate from the competent planning authority.

Instead, the promoter uploaded Form 4 (Architect’s Certificate) dated 2 December 2020 on the MahaRERA portal, declaring that construction was complete. MahaRERA made it clear that such a certificate cannot substitute the statutory requirement of an Occupation Certificate, which alone validates legal possession under RERA.


Contractual Possession Due in 2016, Regulatory Direction in 2018 Ignored

The homebuyers had booked their flats between 2014 and 2015, and their registered Agreements for Sale recorded the contractual possession date as on or before 31 May 2016. Despite substantial payments having been made, possession was not handed over within the agreed timeline.

MahaRERA further noted that the Authority had passed a common order in October 2018, directing the promoter to hand over possession by 31 December 2018. This regulatory direction was also not complied with, and the delay continued unabated.


Promoter Remains Absent, Matters Proceed Ex-Parte

During the proceedings, the promoter remained absent for four consecutive hearings and failed to file any written submissions or documents to justify the delay or counter the homebuyers’ claims.

In view of repeated non-appearance, MahaRERA proceeded ex-parte, observing that the allegations and documents placed on record by the complainants remained uncontroverted.


MahaRERA: No OC Means Delay Continues

In its findings, MahaRERA reiterated that:

  • Architect’s Certificates only attest to construction completion
  • Occupation Certificates are mandatory statutory approvals
  • Possession without OC is impermissible under Sections 17 and 19(10) of the RERA Act

The Authority held that the delay in the project continued until the date of the order, entitling the homebuyers to exit the project and seek refund with interest.


Refund With Interest Ordered From Contractual Due Date

Allowing three of the four complaints, MahaRERA directed the promoter to:

  • Refund the entire amount paid by the allottees (excluding statutory charges such as stamp duty and registration fees)
  • Pay interest from 1 June 2016 until realization, at the rate prescribed under Rule 18 of the Maharashtra RERA Rules, 2017
  • Complete the refund within 60 days of the order
  • Execute and register cancellation deeds after payment

One complaint was dismissed solely due to the absence of a registered Agreement for Sale, which the Authority held to be a foundational document for adjudication.


COVID Moratorium Relief Denied

MahaRERA also ruled that the promoter cannot claim the benefit of COVID-19 moratorium notifications, noting that the delay arose much before the pandemic and was attributable entirely to the promoter’s failure to perform contractual and statutory obligations.


Why the Ruling Matters

The order sends a clear message to developers across Maharashtra that project completion cannot be declared through professional certificates alone. Without an Occupation Certificate issued by the competent authority, buyer rights under RERA remain fully enforceable, including the right to refund with interest.

For homebuyers stuck in delayed projects, the ruling reaffirms that Form 4 cannot be used as a shield against accountability.

Also Read: Homebuyers Can’t Double-Dip: MahaREAT Says Civil Suit Blocks Later RERA Complaints

You May Also Like

Society Redevelopment Gone Wrong: Why RERA Refused to Help Flat Buyers

Mumbai Tribunal rules that once a developer exits a redevelopment project by terminating the agreement, RERA loses jurisdiction. Flat buyers who paid ₹50 lakh each were told to approach Civil Court instead. A must-read warning for all homebuyers in society redevelopment projects.

Housing Society Wins Key Victory in Deemed Conveyance Dispute Against Developer

In a major relief for flat owners, Bombay High Court has ordered deemed conveyance for Rashesh CHS in Bhayandar, granting exclusive rights over 2201.56 sq.m. and proportionate share in recreational ground. A significant win against developer delay.

🏗️ Realty Rally at the Open: Big Developers Shine, Mid-Caps Lose Steam as Markets Kick Off the Day

Real estate stocks opened on a mixed note, with large developers leading early gains amid festive optimism and Q2 momentum, while mid-caps slipped on profit-taking. Investors now await booking updates and volume trends to see if the rally can broaden through the day.

MHADA Awards GTB Nagar Sion Project to Keystone Realtors (Rustomjee Group)

MHADA’s ambitious redevelopment of Punjabi Colony in Sion’s GTB Nagar, Mumbai, is moving forward following crucial legal clearances from the Bombay High Court and Supreme Court. This project aims to transform the historically significant area, originally a refugee settlement for Partition-era migrants, by providing modern homes and additional housing.