Builders Cannot Exclude Land Cost While Reporting Project Revenue, Rules Tribunal

In a key ruling affecting real estate developers, the Income Tax Appellate Tribunal (ITAT) Mumbai has upheld a tax addition of ₹47.26 crore against Relationship Properties Pvt Ltd, holding that land cost and development rights must be included while calculating revenue under the Percentage of Completion Method (POCM).

The decision came in ITA No. 2067/Mum/2024, involving Assessment Year 2017–18, where the developer disputed the tax department’s method of computing project completion.


Background: Real Estate Revenue Calculation Under Scrutiny

Relationship Properties Pvt Ltd was involved in a Bangalore residential project where:

  • Landowners were entitled to 31%
  • Developer (assessee) had 69% development rights

The developer argued that because land did not belong to them, the cost of land should not be included in project cost for calculating percentage completion.

Excluding land cost reduced the completion percentage, resulting in lower revenue recognition for that year.

Initially, the Assessing Officer had proposed a massive addition of ₹229.29 crore, later reduced to ₹47.26 crore after recalculations in a remand report.


Assessee’s Stand: “Land Isn’t Ours, So It Shouldn’t Count”

The company claimed:

  • Only construction cost should be counted
  • Land cost should be excluded since land is owned by landowners
  • Following ICAI Guidance Note, it said only direct construction cost is relevant
  • Recognising more revenue in AY 2017–18 would lead to double taxation, as income was already declared in AY 2018–19

Tax Department’s View: ICAI Guidance Note Supports Us

The Revenue argued:

  • Land/Development Rights are integral to the project and must be included
  • ICAI’s Real Estate Guidance Note clearly states land cost is part of project cost
  • After adjustments, the correct completion percentages were:
    • Phase 1: 66.39%
    • Phase 2A: 39.59%
  • Therefore, revenue must be recognised proportionately

CIT(A) agreed, upholding the revised addition.


Tribunal’s Decision: Land Cost Cannot Be Split From Project Cost

The ITAT observed that:

  • POCM is a legally regulated accounting method
  • Land is an essential component of any real estate development
  • Excluding land artificially suppresses completion percentage
  • ICAI Guidance Note explicitly lists land cost as part of project cost

Given these facts, the Tribunal held that the assessee’s exclusion of land cost was incorrect and upheld the ₹47.26 crore addition.


Impact: Real Estate Developers Must Recheck POCM Calculations

This ruling reinforces that:

  • Builders must include land or development rights in POCM calculations
  • Revenue recognition cannot be deferred by excluding land value
  • Tax planning must align strictly with the ICAI Real Estate Guidance Note

The decision is expected to influence several ongoing assessments, especially joint development agreements where landowners and developers share revenue.

You May Also Like

Indiabulls takes possession of Villas, flats connected to Wadhawans in Mumbai

Indiabulls Commercial Credit Ltd, has taken symbolic possession of three villas, flats…

SRA Dream Turns Nightmare: Kurla Homebuyers Lose Flats Despite Paying Crores

MahaRERA has permitted a fresh RERA registration for the stalled Sapphire I project in Kurla, giving the new developer a clean slate while protecting original allottees through abeyance of the old registration and a lien on reimbursement funds payable to the terminated promoter ITMC

Willingdon View Building: Bombay High Court Orders Evacuation of Floors 17 to 34 Over Fire and OC Violations

In a major blow to residents of Willingdon View CHS in South Mumbai, the Bombay High Court has ordered the evacuation of floors 17 to 34 due to absence of Occupation Certificate and Fire NOC. The court slammed the illegal occupation as a threat to life and directed BMC to take legal action if residents fail to vacate within two weeks.

MHADA Mumbai Lottery 2026: HIG Bags 31.8% of Homes, EWS Gets Just 5.5% – Affordable Housing for the Rich?

MHADA has reserved 610 tenements exclusively for HIG in Kannamwar Nagar–Vikhroli, pushing HIG share to 31.8% while EWS gets only 5.5%. Even after 7.5% price cut, flats cost ₹1.35–1.37 crore. Is MHADA still for the common man?