In a notable order, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has allowed Pune-based developer Gera Developments Private Limited to cancel two apartment bookings in its project “Gera’s Planet of Joy IV” due to repeated non-payment by homebuyers. While the authority upheld the cancellations, it significantly reduced the amount the builder could forfeit.

MahaRERA Member Ravindra Deshpande, in the order dated 07 May 2026, ruled that the Agreements for Sale stand terminated, but restricted the forfeiture to only 2% of the total unit cost — far lower than the nearly 10% plus additional charges (interest, brokerage, and GST) that the developer had demanded.

Cases in Detail

Gera Developments filed two complaints:

  1. CC005000000269618 – Against Mr. Prem Prakash Singh & Mrs. Priyanka Singh for Unit 1201 (12th Floor, F1 Tower). Agreement registered on 11 March 2022.
  2. CC005000000279748 – Against Mr. Ganesh Uttamrao Dhamdhere for Unit G04 (Podium Floor, F1 Tower). Agreement registered on 04 October 2022.

The developer claimed the buyers repeatedly defaulted on installments despite multiple reminders and legal notices issued in 2023. The company invoked Clause 36 of the Agreement and formally terminated both deals.

Builder’s Demand vs RERA Decision

Gera Developments wanted to forfeit around 10% of the basic sale price along with interest, brokerage, and GST components. This would have allowed them to retain over ₹12 lakh in one case and over ₹11.6 lakh in the other.

However, MahaRERA held that while the cancellations were justified due to breach of contract and violation of Section 19(6) of the RERA Act, excessive forfeiture is not permissible. Citing its earlier Order No. 35/2022, the authority limited forfeiture to a reasonable 2% of the total unit cost in both matters.

The builder has been directed to refund the remaining amount paid by the buyers after deducting the 2% forfeiture. The developer must also bear the expenses of executing and registering the cancellation deeds.

Next Steps

The homebuyers have 60 days to execute the Cancellation Deeds. If they fail to do so, Gera Developments can file a non-compliance application under MahaRERA Circular No. 50/2025.

The allottees remained absent during the hearings, which strengthened the developer’s case on the issue of cancellation.

Industry Takeaway

This ruling highlights MahaRERA’s balanced approach — supporting developers against chronic defaulters while preventing unfair profiteering through excessive penalties. The project “Gera’s Planet of Joy IV” is registered under MahaRERA No. P52100031876.

Also Read: MahaRERA Told Homebuyers to Cooperate. Tribunal Tells Builder to Pay Up

You May Also Like

MHADA lottery for 24 homes on August 10, 2020

MHADA the state’s housing body has put a total of 24 homes…

Local trains start for essential services, commoners ready to wait

Local trains in Mumbai have begun once again, though only for essential…

Hrithik Roshan Buys ₹28-Crore Office Space in Juhu’s Premium Yura Project

Bollywood actor Hrithik Roshan has purchased a ₹28-crore commercial space at Yura in Juhu, acquiring 7,000 sq ft across two floors. The Grade-A development is emerging as a premium office hub for Juhu residents.

Paid ₹1.5 Crore, Got No Flat: MahaRERA Rejects Buyer’s Claim Against New Developer

In a setback for homebuyers in redevelopment projects, MahaRERA has dismissed a complaint by a buyer who paid ₹1.5 crore to the original developer. The Authority ruled that the new developer cannot be held liable after the society lawfully terminated the old agreement, leaving the buyer to pursue remedies only against Zaveri Constructions.