The Maharashtra Real Estate Regulatory Authority (MahaRERA) has reinstated a non-compliance case against Kavya Mira Realty, following a complaint by B.K. Finance Corporation Pvt. Ltd. regarding delayed possession of a property. The case, originally dismissed due to procedural issues, has now been restored and transferred to the Adjudicating Officer for further action.

Background of the Case

The case dates back to July 25, 2019, when the complainant filed a grievance under Section 18 of RERA, seeking compensation for the delay in possession of a property. MahaRERA issued a final order on December 14, 2021, instructing the developer to pay interest from February 1, 2015, until possession with an occupancy certificate was provided.

However, as the developer failed to comply, the complainant filed a non-compliance application on April 12, 2022, demanding enforcement of the order.

Dismissal and Restoration of the Case

On July 4, 2023, MahaRERA dismissed the non-compliance application, citing:

  • The complainant had already filed a civil suit in the Thane district court and a cheque dishonor case under Section 138 of the Negotiable Instruments Act.
  • The complainant failed to attend the scheduled hearing, leading to the assumption that they were not pursuing the case further.

However, the complainant later filed a restoration application, arguing that they were unaware of the hearing due to technical issues and had no deliberate intent to remain absent.

MahaRERA’s Latest Ruling

During a virtual hearing on November 28, 2024, MahaRERA observed that:

  • The respondent (Kavya Mira Realty) failed to appear for three consecutive hearings, leading to an ex-parte decision.
  • The complainant had genuine difficulties in accessing the hearing and should not be penalized on procedural grounds.

As a result, MahaRERA has restored the non-compliance case and directed its transfer to the Adjudicating Officer for further legal proceedings. The MahaRERA Registry has been instructed to facilitate the transfer.

Implications for Homebuyers

This ruling reaffirms MahaRERA’s commitment to protecting homebuyers’ rights and ensuring developers comply with their obligations. The decision highlights the importance of accountability in the real estate sector, giving hope to other buyers facing possession delays and non-compliance issues.

The MahaRERA order was passed on February 12, 2025, following a virtual hearing, after the matter was reserved for order on November 28, 2024.

📍 Stay tuned for further updates on this case and more real estate news!

Also Read: maharera exam

You May Also Like

For the First Time India Achieved Top 10 Global Rank for Real Estate Transparency

India has made history by entering the top 10 in JLL’s Global Real Estate Transparency Index (GRETI) 2024. This achievement reflects the country’s progress in financial regulation, climate risk disclosure, and streamlined building regulations. Despite notable improvements, India faces challenges in dispute resolution and data access.

MahaRERA Orders Refund with Interest in Serenity Project Case, Dismisses Premature Complaints

In a crucial ruling, MahaRERA has directed JVPD Properties Private Limited to refund homebuyers of the delayed Serenity – BLDG 1 project with interest as per Maharashtra RERA Rules. While two complaints were upheld, four were dismissed as premature, including an attempt to hold Xander Finance Pvt. Ltd. responsible for project completion. MahaRERA has given the developer 60 days to comply with the refund order, reinforcing its stance on protecting homebuyers from undue delays.

Top 8 Listed Developers Slash Debt by 54% in Q1 FY25

The top eight listed developers in India have reduced their net debt by 54% in Q1 FY25, supported by a significant increase in booking values. The surge in residential sales across key cities marks a strong recovery in the sector.

Mumbai Woman Bought Flat in 2007, Builder Wrote It in 2011 — Tax Dept Pounced

Mumbai woman’s LTCG claim survives — ITAT rules builder’s delayed ledger entry can’t override actual 2007 allotment date. ₹17L addition deleted.