A homebuyer’s attempt to challenge a MahaRERA order failed—not on merits, but on technical lapses in filing the appeal. In a sharply reasoned order, the Maharashtra Real Estate Appellate Tribunal, Mumbai, held that unsigned, unaffirmed, and unnotarized appeal documents cannot constitute a valid appeal, resulting in the outright dismissal of the homebuyer’s case.

The ruling came in M.A. No. 751 of 2025 (Delay) in Appeal No. AT06/00319/2025, between allottee Anubhav Virmani and promoter Kanakia Spaces Realty Pvt. Ltd., and underscores how procedural mistakes can completely extinguish a homebuyer’s appellate rights under RERA.


What Triggered the Homebuyer’s Loss

The homebuyer sought to appeal against a MahaRERA Authority order dated 30 January 2025, which had dismissed his complaint as premature.
Under Section 44 of the RERA Act, an appeal must be filed within 60 days, i.e., by 30 March 2025.

The allottee claimed:

  • Appeal was filed online on 08 April 2025
  • Delay was only 8 days
  • Delay occurred due to frequent professional travel

On this basis, a delay condonation application was filed.


Developer’s Advocate Exposes Critical Filing Defects

The decisive blow to the homebuyer’s case came from Advocate Vinod Talreja, appearing for Kanakia Spaces Realty Pvt. Ltd., who highlighted serious procedural defects in the appeal filing.

Adv. Talreja pointed out that:

  • The appeal memo uploaded on 08.04.2025 was unsigned
  • It was neither affirmed nor notarized
  • No vakalatnama or authorization existed on the claimed filing date
  • All documents—including affidavits and appeal memo—were signed, affirmed, and notarized only on 04 August 2025

Based on these defects, Adv. Talreja argued that:

An unsigned and unexecuted appeal cannot be treated as a valid appeal in law, and such filing does not stop the clock of limitation.

This argument proved pivotal.


Tribunal’s Finding: No Valid Appeal Without Proper Execution

The Appellate Tribunal, comprising Justice S.S. Shinde (Chairperson) and Shri Shrikant M. Deshpande (Member A), accepted the promoter’s submissions and held that:

Unsigned, unaffirmed, and unnotarized documents do not constitute a valid appeal.

Relying on Order XLI Rule 1 of the CPC and the MahaRERA Appellate Tribunal Regulations, 2019, the Tribunal ruled that:

  • Mere online uploading of defective documents is insufficient
  • An appeal becomes valid only when duly signed and executed

From 8 Days to 125 Days: How the Delay Ballooned

On the basis of Adv. Talreja’s submissions, the Tribunal concluded that:

  • The appeal became legally valid only on 04 August 2025
  • Limitation expired on 30 March 2025
  • Actual delay was 125 days, not 8 days

The Tribunal found that the homebuyer:

  • Suppressed material facts
  • Misrepresented the length of delay
  • Did not approach the Tribunal with clean hands

Travel Excuse Rejected Despite Homebuyer’s Plea

The homebuyer, represented by Advocate Aman Shukla, argued that frequent travel for professional commitments caused the delay.

However, the Tribunal rejected this explanation, observing that:

  • No compelling or documented reasons were shown
  • No explanation was given for long periods of inactivity while in Mumbai
  • In the digital era, appeals can be prepared and filed remotely
  • Routine professional travel cannot override statutory limitation

Tribunal Warns Against Misuse of Online Filing

In strong words, the Tribunal cautioned that:

  • Allowing defective appeals to be cured months later would create a dangerous precedent
  • Parties could manipulate limitation by uploading unsigned documents
  • Such practices would undermine the substantive law of limitation

Final Outcome: Homebuyer’s Appeal Ends Without Merits Hearing

  • Delay condonation application rejected
  • Appeal dismissed as non-maintainable
  • No examination of the homebuyer’s grievance on merits
  • Parties directed to bear their own costs

Why This Order Is a Wake-Up Call for Homebuyers

This case is a stark reminder that:

  • Technical compliance is as critical as substantive rights
  • Even genuine grievances can fail due to procedural lapses
  • RERA’s appellate process is unforgiving of defective filings

For homebuyers, the message is clear:

A single technical mistake can cost the entire appeal.

Also Read: MahaRERA Dismisses Complaint Against Developer Over Redevelopment Dispute

You May Also Like

🏗️ Realty Stocks Open Steady as Markets Kick Off; Sector Poised for Intraday Moves

Realty stocks began the session on a steady note, with large developers gaining early interest while mid-caps traded mixed. The sector is in consolidation as investors await triggers through the day.

Indian Real Estate Sector Received Institutional Investments Worth USD 1.6 Bn 

Indian Real Estate Sector Received Institutional Investments Worth USD 1.6 Bn in…

🏗️ Prestige Group Expands Mumbai Footprint with ₹2,000 Cr ‘Prestige Garden Trails’ Launch in Dahisar–Mira Road Corridor

Prestige Group expands its Mumbai footprint with the launch of Prestige Garden Trails in Dahisar–Mira Road — a ₹2,000 crore mid-segment residential project that blends quality, connectivity, and community living in one of Mumbai’s fastest-growing corridors.

Butlr Technologies Announces Partnership with Propstack for
Occupancy Sensing in India

Butlr, the leading people sensing platform, announced a partnership with Propstack, India’s…