-MahaRERA extends project’s deadline without prejudice to homebuyer’s rights

-Sole aim is to get a stalled or stressed housing project completed and homebuyer’s interest stays protected

-Deadline extension is permitted only after due diligence and receiving project completion’s guarantee

The Maharashtra Real Estate Regulatory Authority (MahaRERA) permits deadline extension to any housing project only to protect homebuyer’s interest and with certain conditions on the developer.

Even while the project’s deadline is extended, a homebuyer’s rights remain intact. If a flat purchaser does not get possession as per laid down timeline, he/ she can move MahaRERA, as per the regulations. It is the homebuyer’s right to move the housing regulator, should there be any violation of Real Estate (Regulation and Development) Act, 2016.

In case if a certain housing project fails to meet the extended deadline of a year, the developer is permitted to file for another additional time only after securing 51% consent from the homebuyers. Although the homebuyers provide their consent, their rights under the Real Estate (Regulation and Development) Act, 2016 do not get diluted. The aggrieved flat purchaser can continue to get a fair trial on the petition already filed or intends to move MahaRERA against the project/ developer.

In a scenario if a developer fails to secure 51% consent of the homebuyers, the MahaRERA has the right to grant conditional extension to the project, which was stalled for over a year.

MahaRERA’s only objective is to protect homebuyer’s interest.
Extensions are given after examining the reasons for delay and the efforts that the developer will put in to complete the project during the extended time. Extension is given after a due hearing and by imposing conditions to ensure project’s completion.

“Homebuyers usually put in their life’s savings to buy a home and are emotional about the same. There have been some people complaining that MahaRERA grants extension to projects, despite their grievances filed. I would like to reiterate the obvious, MahaRERA gives extension only after strict scrutiny of all such proposals and reasonable conditions to complete the stalled project. MahaRERA’s aim is to ensure a residential project gets completed under any circumstances and homebuyers get their rightful shelter. Grant of extension is conditional and all the rights of homebuyers remain intact,” said Ajoy Mehta, Chairman, MahaRERA.

Also Read: MahaRERA: Those submitting Quarterly Progress Report (QPR) without notice has increased from 0.03% in January 2023 to 52.60% in June 2023

You May Also Like

MHADA Sets One-Month Deadline for Action on Illegal Construction in Abhyudayanagar

During MHADA’s Eighth Lokshahi Day, officials addressed complaints about illegal construction on the terrace of Suruchi Cooperative Housing Society in Abhyudayanagar. A one-month timeline was set for action following a directive to the Executive Engineer to survey the site, prepare a report, and submit it to the Encroachment Removal Cell. This move underscores MHADA’s commitment to tackling encroachment issues.

Parties to shift from pubs to home, post lockdown

Parties which for many in cities has become an integral part of…

Business Confidence Rises as Demand Grows and Interest Rates Decline: Colliers APAC Cap Rate Report Q4 2024

Colliers’ Q4 2024 APAC Cap Rates report highlights rising business confidence, strong commercial uptake in Mumbai and Bengaluru, and stable capital rates despite increased supply.

Vaastu the biggest influencer for homebuyers

Vaastu has come out as the biggest influencer for home buyers when…