The Maharashtra Real Estate Regulatory Authority (MahaRERA) has granted a three-year extension to developer S D Corporation Pvt. Ltd. for its project “Siennaa Wing F” in Kandivali (Maharera Registration No. P51800019693), but with strict conditions to protect homebuyers’ interests.

While the promoter sought an extension until December 30, 2027, MahaRERA made it clear that this relief will not come without transparency and accountability. The Authority has directed the builder to submit detailed project milestones and share them with all homebuyers so that progress can be closely tracked.


📝 Background of the Case

The project was originally supposed to be completed by December 31, 2023, but after multiple extensions due to the COVID-19 pandemic, the deadline was pushed to December 30, 2024.

The developer applied for a further extension under Section 7(3) of the RERA Act, citing pandemic-related disruptions such as labour migration, supply chain issues, rising costs, and delays in fund disbursement.

However, the promoter could not obtain the required 51% consent from allottees, which is typically necessary for such extensions.


🧾 Why MahaRERA Granted the Extension

MahaRERA noted that not granting the extension could halt the project entirely, leaving homebuyers in limbo. To avoid this, the Authority allowed the extension but invoked its powers under Section 7(3), which enables it to impose additional terms and conditions while keeping the project registration active.

The aim, MahaRERA stated, is to protect homebuyers’ interests while ensuring the project is completed efficiently.


📌 Key Conditions Imposed by MahaRERA

  • 🏗 Submission of Milestone Chart:
    The promoter must submit PERT/CPM or Bar Charts detailing project milestones within 15 days of the order.
  • 📤 Sharing with Homebuyers:
    These timelines must be shared with all homebuyers, ensuring they have a clear view of the builder’s commitments.
  • 📅 Monthly Progress Reports:
    The promoter must file monthly updates with MahaRERA and the homebuyers’ association, detailing achievements and any delays.
  • 📝 Occupancy Certificate (OC) Updates:
    Once partial or full OC is received, the developer must update MahaRERA and the project’s online portal.

These measures are designed to create a continuous monitoring mechanism — ensuring that the developer remains accountable throughout the extended timeline.


🏡 Why This Matters to Homebuyers

This order is significant because it shows MahaRERA’s dual approach — granting flexibility to developers when justified, but simultaneously tightening oversight to protect homebuyers.

By mandating milestone disclosures and monthly reporting, MahaRERA ensures that buyers are no longer kept in the dark, and the Authority can step in if there’s any deviation from the approved schedule.

Also Read: MahaRERA fine Builders for printing ads without MahaRERA number

You May Also Like

HDFC Capital Ties Up with DivyaSree-backed CLS to Launch ₹1,000 Cr Institutional Rental Housing Platform

HDFC Capital has partnered with DivyaSree Group-promoted Curated Living Solutions to establish a ₹1,000 crore platform focused on developing and operating institutional-grade rental housing across India’s major urban centres.

August 2021 sells more Homes than Aug 2019 but less than July 2021

August 2021 saw more sales than it sold in August 2019, but…

Shapoorji Pallonji Real Estate, Indiabulls Finance and PAG collaborate for India’s tallest luxury tower

Shapoorji Pallonji Real Estate, Indiabulls Finance and PAG collaborate for India’s tallest…

Project deadline is extended only after receiving Guarantee of completion: MahaRERA

-MahaRERA extends project’s deadline without prejudice to homebuyer’s rights -Sole aim is…