MahaRERA holds developer at fault for issuing allotment before full booking amount; directs refund of ₹1.50 lakh

In a significant order strengthening homebuyer protections, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has ruled that a booking application form by itself does not amount to a concluded or binding sale contract, especially when the booking process is incomplete.

The Authority directed Mahindra Happinest Developers Ltd to refund ₹1.50 lakh to a homebuyer who had cancelled her booking before paying the second instalment of the booking amount.

The ruling came in Complaint No. CC006000000194936, filed by Moushumi Rohan Gala, concerning a flat booked in the developer’s Mahindra Happinest Kalyan Project.


What Was the Dispute About?

The complainant had booked a 1 BHK apartment in August 2020 and paid:

  • ₹25,000 as token amount
  • ₹1,25,000 as Booking Amount–1

The second instalment (Booking Amount–2) was due on October 9, 2020. However, due to COVID-related travel restrictions, the complainant—who was residing in Qatar—requested time for registration.

Despite this, the developer:

  • Issued an allotment letter before receiving the full booking amount
  • Sent repeated reminders for registration
  • Eventually forfeited the entire ₹1.50 lakh when the complainant cancelled the booking one day before the second instalment due date

Aggrieved, the homebuyer approached MahaRERA seeking a refund.


Developer’s Argument: Booking Form Is a Binding Contract

The developer argued that:

  • The booking application form constituted a concluded contract
  • The complainant had voluntarily cancelled the booking due to “personal circumstances”
  • As per the booking terms, the developer was entitled to forfeit 10% of the total flat cost
  • Issuing the allotment letter created enforceable contractual obligations

The developer also cited Supreme Court judgments supporting forfeiture of earnest money.


MahaRERA’s Key Finding: No Completed Booking, No Binding Contract

Rejecting the developer’s stand, MahaRERA held that:

“Signing of the booking form does not in itself create a binding contract.”

The Authority noted that as per the booking terms:

  • The booking would be completed only after payment of both Booking Amount–1 and Booking Amount–2
  • The developer was required to issue the allotment letter after receiving the full booking amount

By issuing the allotment letter before receiving Booking Amount–2, the developer violated its own booking conditions.


Why Issuing Allotment Letter Early Hurt the Developer’s Case

MahaRERA observed that:

  • The developer acted prematurely and contrary to the agreed process
  • The complainant cancelled the booking before the due date of the second instalment
  • The booking transaction was never completed
  • Mere issuance of an allotment letter cannot justify forfeiture when conditions precedent were not fulfilled

Flat Was Resold, No Loss to Developer

A crucial factor influencing the decision was that:

  • The same flat was later sold to a third party
  • A registered agreement for sale was executed in March 2021
  • The developer suffered no actual financial loss

Hence, MahaRERA ruled that forfeiture of the entire booking amount was unjustified and against the spirit of RERA, which is consumer-protective legislation.


Final Order by MahaRERA

MahaRERA directed the developer to:

  • Refund ₹1,50,000 (token + Booking Amount–1)
  • Pay the refund within 30 days
  • Failing which, pay interest at 2% above SBI’s MCLR
  • No order as to costs

Why This Order Is Important for Homebuyers

This ruling is significant because it clarifies that:

  • Booking forms are not equal to sale agreements
  • ❌ Developers cannot forfeit money if booking is incomplete
  • ❌ Allotment letters issued prematurely do not create binding rights
  • ✅ Refunds are justified when developers breach their own booking terms
  • ✅ RERA will look at substance over paperwork

Key Takeaway

Homebuyers should note that payment milestones matter, and developers must strictly follow their own booking procedures. MahaRERA has once again reinforced that consumer interest comes first, even when standard forfeiture clauses exist.

Also Read: MahaRERA Appellate Tribunal Rejects Developer’s Appeal Over Delay in Filing

You May Also Like

⚡ Builder Sold Flat… Then Mortgaged It! MahaRERA Tribunal; Says Builder Must Clear Mortgage, Give Possession & Pay Interest

MahaREAT has upheld a MahaRERA order directing Lokhandwala Kataria Construction to clear an illegal mortgage, hand over OC-backed possession, and pay delay interest to homebuyer Faisal Sabir Rashid. The builder had mortgaged the flat after selling it, violating RERA. The appellate ruling makes the 2024 order final and enforceable.

Indian Realty Stocks Open Firm as Markets Signal Positive Start; Key Developers Show Mixed Trend

Indian real estate shares began the session on a steady note as markets hinted at a gap-up opening. The Nifty Realty index edged higher, with selective buying seen in stocks like Oberoi Realty, while others such as Godrej Properties remained under pressure, signaling a stock-specific trading day ahead.

Cheer for homebuyers as Maha Govt maintains status quo on ready reckoner rates for FY25 

Homebuyers in Maharashtra can cheer before the auspicious occasions of Gudi Padwa and…

Housing Sales Drop 4% in India’s Top Tier-2 Cities in Q3 2025; New Launches Slide 10%

A new PropEquity report shows housing sales in India’s top 15 tier-2 cities fell 4% YoY in Q3 2025, while new launches declined 10%. Despite the slowdown, sales value rose 4%, reflecting a shift toward premium housing. Ahmedabad led in volumes, while Bhubaneshwar recorded the sharpest fall.