MahaRERA Orders Refund With Interest as Homebuyers Win Long-Running Delay Battle

In a significant ruling reinforcing homebuyer protections under the Real Estate (Regulation and Development) Act, 2016, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has categorically held that uploading Form 4 (Architect’s Certificate) does not amount to legal project completion in the absence of an Occupation Certificate (OC).

The Authority passed the order while deciding a batch of complaints filed by homebuyers in the “Kuber Ganraj” project (MahaRERA Registration No. P51700008998), developed by promoter Ashvinkumar Dahyabhai Patel. The ruling resulted in refunds with interest being granted to three allottees after years of delay.


Form 4 Uploaded, But Project Still Without OC

As recorded by MahaRERA, the project was originally scheduled for completion in 2018, with a revised completion date of 2019. However, the project never obtained an Occupation Certificate from the competent planning authority.

Instead, the promoter uploaded Form 4 (Architect’s Certificate) dated 2 December 2020 on the MahaRERA portal, declaring that construction was complete. MahaRERA made it clear that such a certificate cannot substitute the statutory requirement of an Occupation Certificate, which alone validates legal possession under RERA.


Contractual Possession Due in 2016, Regulatory Direction in 2018 Ignored

The homebuyers had booked their flats between 2014 and 2015, and their registered Agreements for Sale recorded the contractual possession date as on or before 31 May 2016. Despite substantial payments having been made, possession was not handed over within the agreed timeline.

MahaRERA further noted that the Authority had passed a common order in October 2018, directing the promoter to hand over possession by 31 December 2018. This regulatory direction was also not complied with, and the delay continued unabated.


Promoter Remains Absent, Matters Proceed Ex-Parte

During the proceedings, the promoter remained absent for four consecutive hearings and failed to file any written submissions or documents to justify the delay or counter the homebuyers’ claims.

In view of repeated non-appearance, MahaRERA proceeded ex-parte, observing that the allegations and documents placed on record by the complainants remained uncontroverted.


MahaRERA: No OC Means Delay Continues

In its findings, MahaRERA reiterated that:

  • Architect’s Certificates only attest to construction completion
  • Occupation Certificates are mandatory statutory approvals
  • Possession without OC is impermissible under Sections 17 and 19(10) of the RERA Act

The Authority held that the delay in the project continued until the date of the order, entitling the homebuyers to exit the project and seek refund with interest.


Refund With Interest Ordered From Contractual Due Date

Allowing three of the four complaints, MahaRERA directed the promoter to:

  • Refund the entire amount paid by the allottees (excluding statutory charges such as stamp duty and registration fees)
  • Pay interest from 1 June 2016 until realization, at the rate prescribed under Rule 18 of the Maharashtra RERA Rules, 2017
  • Complete the refund within 60 days of the order
  • Execute and register cancellation deeds after payment

One complaint was dismissed solely due to the absence of a registered Agreement for Sale, which the Authority held to be a foundational document for adjudication.


COVID Moratorium Relief Denied

MahaRERA also ruled that the promoter cannot claim the benefit of COVID-19 moratorium notifications, noting that the delay arose much before the pandemic and was attributable entirely to the promoter’s failure to perform contractual and statutory obligations.


Why the Ruling Matters

The order sends a clear message to developers across Maharashtra that project completion cannot be declared through professional certificates alone. Without an Occupation Certificate issued by the competent authority, buyer rights under RERA remain fully enforceable, including the right to refund with interest.

For homebuyers stuck in delayed projects, the ruling reaffirms that Form 4 cannot be used as a shield against accountability.

Also Read: Homebuyers Can’t Double-Dip: MahaREAT Says Civil Suit Blocks Later RERA Complaints

You May Also Like

MHADA issues Tender for Abhyudaya Nagar Redevelopment

The Mumbai Board of MHADA has released a tender for the redevelopment of Abhyudaya Nagar Colony, following government approval. This project aims to improve living conditions for approximately 15,000 residents, offering modern amenities and expanded living spaces after years of delays.

Dispute Over Society Membership Balloons from 23 to 61 – High Court Refuses to Intervene, Calls It Factual Matter Needing Evidence

The Bombay High Court on March 6, 2026, dismissed a petition alleging a co-op society’s voters’ list ballooned from 23 to 61 members, ruling petitioners ignored the objection remedy and that factual disputes require evidence, not writ jurisdiction.

Godrej Properties declared the highest bidder for land parcels in Sector 146, NOIDA 

Godrej Properties Ltd today announced that it has been declared the highest…

ALL IN THE NAME OF POOR! The Detrimental Impact of DCR 33(11)

It’s a matter of great concern for all Mumbaites that successive governments have shown little interest in resolving the burning issue of housing, including the recent phenomenon of private property redevelopment. This article exposes how new DC regulations, particularly DCR 33(11), are ironically worsening the city’s housing crisis in the name of the poor.