In a significant pro-homebuyer ruling, the Maharashtra Real Estate Appellate Tribunal (MahaREAT) has clarified that “soft possession” or “fit-out possession” handed over by a developer without an Occupation Certificate (OC) does not qualify as lawful possession under the Real Estate (Regulation and Development) Act, 2016 (RERA). This means homebuyers can still claim interest for delay in possession even if they have taken physical access to the flat for interiors or partial use.

The judgement was delivered on 23 June 2025 in Appeal No. AT005000000235139 of 2024 (Lalit Rade vs. Atul Ratnakar Mahashabde), overturning an earlier dismissal by the Maharashtra Real Estate Regulatory Authority (MahaRERA).

Case Background and Facts

  • Homebuyer Lalit Rade booked a flat (No. 925, carpet area ≈513.46 sq.ft.) in the project “Tropica Phase-II” (MahaRERA Registration No. P2100008711, Pune), developed by Omkar Developers (with Atul Ratnakar Mahashabde as partner).
  • The registered Agreement for Sale was executed on 9 March 2017, promising possession within 30 months + 6 months grace period (due date: effectively 6/9 September 2019).
  • The buyer paid the full consideration of ₹36,94,150/- plus ₹2,83,428/- GST.
  • The developer failed to deliver possession by the agreed date and had not obtained the OC even years later.
  • In 2022, the buyer filed a complaint before MahaRERA seeking possession with OC, amenities, and interest for delay under Section 18 of RERA.

MahaRERA’s Impugned Order (19 April 2024) MahaRERA dismissed the complaint, reasoning:

  • “Soft possession” was allegedly given on 23 September 2023 via conciliation.
  • Interest claim was an “afterthought” since possession was taken.
  • No cause of action survived under Section 18 for possession.
  • Amenity/defect issues were premature without OC.

MahaREAT’s Landmark Ruling The Tribunal (Coram: Justice S.S. Shinde, Chairperson, and Member Shrikant M. Deshpande) heard the appeal ex-parte (developer did not appear) and allowed it fully. Key holdings:

  1. No successful conciliation existed — Records showed conciliation failed in 2019, and the matter was referred back for adjudication. The Authority wrongly assumed settlement and soft possession.
  2. Soft/fit-out possession without OC is not lawful — Possession under RERA means handing over a completed, habitable flat with valid OC from the competent authority. Anything less (e.g., access for fit-outs while construction/approvals pending) does not discharge the developer’s obligation.
  3. Right to interest under Section 18 is absolute and indefeasible — Citing Supreme Court judgements in Imperia Structures Ltd. vs. Anil Patni (2020) and Newtech Promoters vs. State of UP (2021), the Tribunal held that once delay occurs beyond the agreed date (and buyer is not at fault), interest is payable unconditionally till lawful possession with OC. Full payment by buyer and no fault on their part strengthen the claim.
  4. Developer’s liability continues — The promoter remains bound to obtain OC and hand over lawful possession.

Directions Issued

  • Set aside the MahaRERA order of 19 April 2024.
  • Developer to pay interest on ₹36,94,150/- at SBI’s highest MCLR + 2%:
    • From 7 September 2019 till 23 June 2025 — payable within 30 days.
    • If delayed, further interest on outstanding amount (as on 23 July 2025) till realization.
    • Continuing interest at same rate from date of order till OC is obtained.
  • Developer to obtain OC and hand over lawful possession with OC.
  • Parties bear own costs.

Why This Matters for Homebuyers This ruling reinforces that developers cannot use “soft possession” as a tactic to escape interest liability for years-long delays. Homebuyers should:

  • Insist on possession only with valid OC and all amenities.
  • Not accept soft possession if it risks waiving delay compensation claims.
  • Approach RERA/MahaREAT promptly for interest even after partial access.

Such judgements strengthen buyer protections under RERA and deter incomplete handovers.

Also Read: What Is Carpet Area?

You May Also Like

Why Every Home Needs Lord Ganesha: Mantras, Shlokas & Spiritual Power for Prosperity

Thinking of bringing peace and prosperity to your home? Discover why Lord Ganesha is a must in every household, along with powerful mantras and shlokas to remove obstacles and energize your space.

Maharashtra Announces Fee Waiver for Transgender Students, Orders Universities to Add ‘Third Gender’ Option in Admissions

The Maharashtra government has directed universities to waive academic fees for transgender students and introduce a “Third Gender” option in admission forms, aiming to improve access to higher education and ensure inclusive campuses across the state.

Listed Developers’ Cost of Debt Shrinks to 9% 

Listed Developers’ Cost of Debt Shrinks to 9% in FY23 from 10.3%…

Victory for Small Shopkeepers in SRA Projects: Authority Fixes Reasonable Rate for Extra Area in Goregaon Slum Rehab

Shopkeepers in Goregaon’s Aman Shanti SRA project get major relief as the Slum Rehabilitation Authority orders the developer to sell extra shop space beyond 225 sq.ft. at a fair rate of up to ₹21,000 per sq.ft. – matching what most others already accepted. The January 2026 order directs immediate registration of agreements, ending a years-long dispute and helping the redevelopment move forward for hundreds of families.