The state government on May 4 came out with a circular that has clearly asked MHADA to seek its permission before giving out this NOC.

By Varun Singh

One May 4, the Maharashtra government’s Housing Department came out with a new circular. This circular is directed to MHADA.

The circular issued by the state government is in regards to the redevelopment of cessed buildings under Development Control Rules 33(7).

Till 2011, an FSI of 2.5 was granted for redeveloping cessed dilapidated building within Mumbai city later the FSI was increased to 3.

MHADA issues a No Objection Certificate for carrying out the redevelopment. This NOC is issued by Mumbai Repair and Reconstruction Board of MHADA

Those developers who were issued NOC for 2.5 FSI and wanted to convert the project into a 3 FSI, would approach MHADA and get a new NOC.

However, the new circular has clearly stated that now projects for which NOC are being issued for 3 FSI from 2.5 FSI, MHADA will have to take government’s permission.

Arun Dongare, Chief Officer, Mumbai Repair and Reconstruction Board, said, “The state government’s decision will impact those projects which for the last 9 years haven’t sought the new NOC to convert from 2.5 FSI to 3 FSI. There will be very limited projects in this bracket.”

According to another officer, the state government will seek answers from NOC holders on why so much delay in conversion and will make them accountable. This can also be seen from the words mentioned in the circular issued by the housing department.

The circular reads, “MHADA gives various permissions for redevelopment, but the state government has no information about them. Many complaints in regards to irregularities in such permissions are received by the state government, but as the state government has no information, it cannot resolve them.”

The circular then talks about the NOC given by MHADA in regards to convert a proposal from 2.5 FSI to 3 FSI. “Many a times the NOC given in such cases are not in tandem with the policies of the state government. Thus affecting the image of the government in the eyes of the common citizens.”

The circular also talks about many MLAs and MLCs raising questions related to the same in the assembly and council.

Hence, the government has decided that MHADA before granting a NOC to convert a project into 3 FSI from 2.5 FSI its permission be sought first.

Rajesh Vardhan of Vardhaman Group said, “As one knows that projects that wants to convert from FSI of 2.5 to 3 are old projects and here by this move the government is trying to safeguard the interest of the tenants in such projects. This will not impact new or ongoing projects where NOC of using FSI 3 has already been granted by MHADA.”

Also Read: Diwali Dhamaka Lottery Of 4000 MHADA Homes

Leave a Reply
You May Also Like

Residential Real Estate Supply Rises 12.7% YoY, Premium Segment Grows 14.4%

India’s residential real estate market witnessed a 12.7% YoY supply growth in Q4 2024, driven by Bengaluru (56.1%) and Gurugram (44.1%). The premium segment surged 14.4%, accounting for 52% of new supply, while residential prices grew 22.7% YoY, led by Noida, Greater Noida, and Gurugram. Rising investor activity and sustained demand underscore the sector’s continued growth.

What’s in for the budget 2024-25 for middle class homebuyers?

The budget for the fiscal year 2024-25 was announced by Union Finance…

Fewer Homes Sold, More Money Spent: ₹1 Crore+ Apartments Drive India’s Housing Market in 2025

India’s residential market sold fewer homes in 2025, but buyers spent more as ₹1 crore-plus apartments dominated sales, pushing market value higher despite an 11% fall in unit volumes.

Home Loan Interest to stay in Single Digit

The RBI has decided to keep the Repo Rate that shakes the…