In a landmark ruling that highlights how builders cannot escape liability for their own delays and wrongdoing, the Maharashtra Real Estate Appellate Tribunal (MahaREAT) has overturned a MahaRERA order and ruled entirely in favour of a Thane homebuyer. The case exposes how a promoter delayed registering an agreement for sale despite collecting stamp duty money from the buyer, then attempted to terminate the allotment – only for the Tribunal to set it aside and impose heavy penalties.
Case Details:
- Appeal No.: AT006000000053767 of 2022
- Original Complaint No.: CC006000000078636
- Appellant (Homebuyer): Suchitra Sudam Patil, resident of Block No. 305, Manogat Apartment, Kharegaon, Pakhadi, Kalwa, Thane-400605
- Respondent (Promoter/Builder): Kailash Chattrapati Patil, Shop No.4, Sun Flower Tower, Old Police Line, Parvati Bhavan, Creek Road, Kharkar Ali, Thane (West)
- Project: “Kailash Heights” (RERA Registration No. P51700006977)
- Tribunal Members: Coram – Shri S.S. Shinde (J), Chairperson & Shri Shrikant M. Deshpande, Member (A)
- Reserved on: 13th February 2026
- Pronounced on: 23rd February 2026 (via Video Conferencing)
Chronological Timeline of Events:
- 2011 – Booking and Agreement: In 2011, Suchitra Sudam Patil booked Flat No. 602 on the 6th floor of “Kailash Heights”. On 19 June 2011, she executed an Agreement for Sale with the promoter for a total consideration of ₹35,79,000. She paid ₹12,00,000 (over 33% of the price) as part consideration. Additionally, she paid ₹2,17,000 to the promoter towards stamp duty (₹1,70,000), registration charges (₹38,000), scanning charges (₹2,000), registration agent fees (₹5,000), and a later ₹10,000 instalment – all specifically for registering the agreement.
- Promised Possession Date: The agreement clearly stated possession within 18 months from the date of agreement, i.e., on or before January 2013.
- Builder’s Delay in Registration (2011–2013): Under the Maharashtra Ownership Flats Act (MOFA) Section 4 (and later RERA Section 13), the promoter was obligated to register the agreement after accepting more than 20% (pre-RERA) or 10% (post-RERA) of the consideration. Despite receiving full stamp duty and registration funds from the buyer in 2011, the promoter deposited only ₹1,79,000 towards stamp duty as late as 28 December 2012 – nearly a year late. This caused the original registration challan to expire on 17 April 2013. Meanwhile, government stamp duty rates increased. The promoter then demanded additional stamp duty (around ₹1,00,300 in 2013, later ₹1,00,200 + ₹35,200 penalty in 2017) from the buyer, blaming her for non-cooperation.
- Further Delays and Builder’s Demands (2013–2016): Fresh adjudication was filed in February 2016, but the promoter again failed to pay the deficit amounts. The buyer demonstrated willingness by paying an additional ₹5,00,000 instalment on demand, but the promoter refused to encash the cheque, citing non-payment of interest. The promoter never completed registration.
- Illegal Termination (2016): On 4 August 2016, the promoter issued a termination letter, claiming the buyer failed to register the agreement and come forward for further payments.
- Buyer’s Complaint to MahaRERA (2019): In April 2019, the buyer filed Complaint No. CC006000000078636 seeking registration of the agreement, possession, interest under Section 18 of RERA for delay, and compensation.
- MahaRERA Order (4 April 2022): The Authority dismissed the complaint, holding that without a registered agreement, there was no clear possession date, and parties were bound by original terms for refund. It noted the 2016 termination was unchallenged.
- Appeal to MahaREAT (2022): Aggrieved, the buyer appealed. The promoter did not appear for oral arguments but filed replies claiming the buyer caused delays and the allotment stood terminated.
- Tribunal’s Landmark Judgement (23 February 2026): The Appellate Tribunal set aside the MahaRERA order completely. Key holdings:
- The 2011 Agreement for Sale is valid and binding even unregistered, as non-registration was solely the promoter’s fault (he who prevents a thing from being done cannot benefit from it – citing Supreme Court precedents).
- RERA applies retroactively to ongoing projects (relying on Supreme Court in Newtech Promoters case, 2021).
- Promoter violated MOFA Section 4 and RERA Section 13 by not registering despite receiving >30% payment.
- The 2016 termination is unlawful and set aside – not binding on the buyer.
- Buyer showed full willingness; extra stamp duty/penalty burden falls on promoter due to his delay.
- Delay in possession starts from February 2013 (no force majeure proved).
- Buyer entitled to unconditional interest under RERA Section 18 (citing Bombay High Court in Bombay Dyeing and Neelkamal Realtors cases – even unregistered agreements qualify if terms are clear).
Final Relief Granted to Homebuyer:
- Promoter must register the 19 June 2011 Agreement for Sale within 30 days, at his own cost, without altering terms.
- Pay interest on ₹12,00,000 from 1 February 2013 till realization at SBI’s highest MCLR + 2% (currently 8.70% MCLR for 1-year tenor as of February 2026, so ~10.70% p.a.) – within 30 days, failing which interest continues.
- Complete construction, obtain Occupancy Certificate, and hand over possession of Flat No. 602, subject to buyer paying any genuine balance per the 2011 agreement.
- No third-party rights or encumbrances allowed on the flat.
- Miscellaneous applications disposed of; parties bear own costs.
This ruling is a powerful reminder for homebuyers: Builders cannot exploit procedural lapses they caused themselves. Even pre-RERA deals from 2011 can get full RERA protection if the project was ongoing. Homebuyers facing similar issues should document payments and willingness meticulously – it can turn the tables in appeals.
Also Read: Mumbai Housing Market Slipping: Registration Fall, Rs 1 Cr Homes Disappearing From Market