In a significant ruling that will impact thousands of housing societies built on large phased layouts across Mumbai, the Bombay High Court has held that developers cannot postpone execution of conveyance deeds by citing incomplete development of the entire layout. Justice Sandeep V. Marne, in his order dated 15 June 2026 in Writ Petition No. 11551 of 2025 (Upvan Woodlands Co-operative Housing Society Ltd. vs. Upvan Developers & Ors.), directed the Competent Authority to issue a unilateral deemed conveyance certificate for 2799.90 sq. mtrs. of land in favour of the petitioner society within six weeks.

The Case

The Upvan Woodlands CHS in Upper Govind Nagar, Malad East, was constructed on a portion of a larger five-plot layout admeasuring 4683.80 sq. mtrs. originally owned by Balrampur Chini Mills and later developed by Upvan Developers. The society’s building received its Occupation Certificate in May 2017, and the society was registered in July 2018. Despite repeated demands, the developer refused to execute conveyance, insisting — as per Clause 12 of the MOFA Agreement for Sale — that conveyance would be done only after completion of the entire layout development and sale of all flats in future buildings.

The Competent Authority (District Deputy Registrar, Co-operative Societies) rejected the society’s application for deemed conveyance on 20 May 2025, terming it premature and relying heavily on the contractual clause and the Marathon Era judgment.

Key Legal Findings of the Court

  1. Statutory Timeline Overrides Contractual Clauses The Court emphatically held that the timeline prescribed under Rule 9 of the Maharashtra Ownership Flats Rules, 1964 (conveyance within 4 months of society registration, or a mutually agreed fixed period) prevails over any contractual stipulation. Any clause that defers conveyance until an uncertain future event — such as completion of the entire layout — is void to that extent. The Court relied heavily on its earlier judgment in Lok Housing and Construction Ltd. vs. State of Maharashtra (2025).
  2. Proportionate / Part Conveyance Allowed in Layouts This is the most important takeaway for societies in large phased developments. The Court ruled that societies of completed buildings are entitled to conveyance of their proportionate share of land even before the entire layout is developed. This principle is backed by the Government Resolution dated 22 June 2018 issued by the Cooperation Department.
  3. Misreading of Precedents Clarified The Court clarified that the Marathon Era judgment was wrongly interpreted by the Competent Authority. It does not support the developer’s stand of waiting for full layout completion. The Court also distinguished the Apex Court’s observations in Jayantilal Investments.
  4. FSI and Developer Concerns Addressed While acknowledging that FSI calculations are done on the entire layout, the Court noted that the society had restricted its claim to only 2799.90 sq. mtrs. (as mentioned in the Second Schedule of the agreements). Granting conveyance of this portion will not prevent the developer from completing construction on the remaining plots (148 & 149). The society will have no right to interfere with the balance development beyond the originally disclosed terms.

Significance for Homebuyers and Housing Societies

This judgment is a major boost for homebuyers trapped in large layout projects where developers deliberately delay conveyance to exploit additional FSI/TDR that becomes available over time. By securing ownership of their proportionate land early, societies gain:

  • Marketable title and better property valuation
  • Ability to undertake redevelopment independently if needed
  • Stronger legal position against promoter delays

The ruling reinforces the welfare objective of the Maharashtra Ownership Flats Act (MOFA) and sends a clear message that private contractual clauses cannot defeat statutory protections for flat purchasers.

What Happens Next?

The Competent Authority must now issue the deemed conveyance certificate within six weeks. The developer’s request for stay on the order was rejected by the Court.

Legal experts believe this judgment, along with earlier rulings like ACME Enterprises and Lok Housing, will strengthen the hands of Competent Authorities while deciding similar applications. Societies stuck in similar situations should immediately review their agreements and file (or revive) applications for deemed conveyance.

Also Read: Conveyance Deed has to be registered within 3 months of Receiving OC

You May Also Like

ED Attaches ₹18.10 Crore Assets in 1xBet Case; Probe Finds Illegal Betting Network Using UPI Mule Accounts

The Enforcement Directorate has attached ₹18.10 crore in assets linked to the 1xBet betting case, uncovering a complex network involving mule accounts, UPI payments, and digital ad promotions.

MahaRERA Orders Full Refund with Interest to Homebuyer for Possession Delay

In a significant win for homebuyers, MahaRERA has ruled in favor of a complainant against Viijcon Properties for failing to deliver possession in the Viijcon Cellandine project. The authority ordered a full refund with interest, while dismissing three other complaints due to lack of valid promoter-allottee relationships or incomplete documentation.

Here’s what Real Estate Industry Thinks reduced home sales in Oct

The real estate sector suffered a small set back in October, the…

Housing Sales Value to Cross INR 4.5 Lakh Cr in 2023, From INR 3.27 Lakh Cr in 2022

Homes worth INR 3.49 Lakh Cr. already sold across the top 7…