In a significant victory for homebuyers, the Maharashtra Real Estate Appellate Tribunal has strongly corrected a MahaRERA order and directed Omkar Realtors and Developers Pvt Ltd to refund the entire amount paid by a family for a flat in the Omkar 1973 project — along with interest calculated from the date of payment in 2016.

The case pertains to Unit No. 3502 on the 35th floor of Tower C in Omkar 1973, Worli. Here is the complete chronological sequence of events:

  • March 2015 – April 2016: The Mehta family (Mr Mahendra Mehta, Mr Vikram Mehta and Mrs Hinal Mehta) applied for and received a Letter of Allotment dated 26 April 2016 for the flat. They paid ₹7.33 crore as advance consideration plus ₹35.41 lakh towards TDS, Service Tax and VAT — a total of ₹7.69 crore. The allotment letter promised possession on or before 30 June 2019, extendable latest to 30 June 2020.
  • 2018: Construction of Tower C came to a complete standstill after multiple Bombay High Court orders restrained the developer from carrying out further construction and creating any third-party interest on the top floors. On 1 August 2018, the Mehtas issued a legal notice demanding full refund with 14% interest and cancellation of the allotment.
  • 2021: With no response or refund from the developer, the family approached MahaRERA by filing Complaint No. CC009000000195169 of 2021.
  • 19 December 2022: MahaRERA Member-I directed Omkar Realtors to refund the amount paid. However, the Authority allowed the builder to deduct 2% of the total consideration (as per MahaRERA Order No. 35 of 2022) and crucially denied any interest on the refunded sum.
  • 2023: Aggrieved by the absence of interest and the 2% deduction, the Mehta family filed Appeal No. AT006000000144304 of 2023 before the Maharashtra Real Estate Appellate Tribunal.
  • 23 March 2026: The appeal was heard through video conferencing.
  • 8 April 2026: In a detailed judgment authored by Member (A) Dr Rajagopal Devara (and concurred by Member (J) Shriram R. Jagtap), the Appellate Tribunal allowed the appeal. It held that under Sections 18(1)(a) and 19(4) of the RERA Act, the allottees have an “unqualified right” to full refund along with interest when the promoter fails to deliver possession. The Tribunal ruled that the delay was solely attributable to the builder and court orders, not the homebuyers. It set aside the 2% deduction and the denial of interest.

The Tribunal modified the MahaRERA order and directed Omkar Realtors to refund the full ₹7.69 crore along with interest at SBI MCLR + 2% per annum, calculated from the respective dates of payment till actual realisation. Parties are to bear their own costs.

Advocate Akash Rebello appeared for the homebuyers, while Advocate Sonali Jain represented the developer.

This order is seen as a strong reinforcement of homebuyer rights under RERA, especially in cases where projects are stalled due to the promoter’s litigation issues.

Also Read: Omkar Sells 9 Flats Worth ₹131 Crore To A Buyer

You May Also Like

Mittal Builders Strengthens Presence in Matunga with Premium Redevelopment Projects

Mittal Builders is expanding its footprint in Matunga with a premium redevelopment project alongside Godrej Properties, while evaluating new opportunities in Five Gardens and Wadala.

Modern Real Estate Investment Approaches Empowering Retail Investors in Long-Term Wealth Building

By Prudhvi Reddy, Founder and Chief Executive Officer, Assetmonk In the fast-paced…

Hiranandani partners with Padukone Sports

Hiranandani Group has partnered with Padukone Sports Management to promote badminton among…

Your Stalled Dream Home Could Finally Be Yours: New IBBI Report Offers Lifeline to Lakhs of Trapped Homebuyers

Homebuyers trapped in over 553 stalled projects affecting 1.08 lakh families finally have real hope. The new IBBI report, submitted last week on Supreme Court orders, promises project-wise resolution, ring-fenced funds, and a completion-first approach instead of liquidation. Here’s exactly how it could change your wait for possession forever.