In a significant victory for homebuyers, the Maharashtra Real Estate Appellate Tribunal has strongly corrected a MahaRERA order and directed Omkar Realtors and Developers Pvt Ltd to refund the entire amount paid by a family for a flat in the Omkar 1973 project — along with interest calculated from the date of payment in 2016.

The case pertains to Unit No. 3502 on the 35th floor of Tower C in Omkar 1973, Worli. Here is the complete chronological sequence of events:

  • March 2015 – April 2016: The Mehta family (Mr Mahendra Mehta, Mr Vikram Mehta and Mrs Hinal Mehta) applied for and received a Letter of Allotment dated 26 April 2016 for the flat. They paid ₹7.33 crore as advance consideration plus ₹35.41 lakh towards TDS, Service Tax and VAT — a total of ₹7.69 crore. The allotment letter promised possession on or before 30 June 2019, extendable latest to 30 June 2020.
  • 2018: Construction of Tower C came to a complete standstill after multiple Bombay High Court orders restrained the developer from carrying out further construction and creating any third-party interest on the top floors. On 1 August 2018, the Mehtas issued a legal notice demanding full refund with 14% interest and cancellation of the allotment.
  • 2021: With no response or refund from the developer, the family approached MahaRERA by filing Complaint No. CC009000000195169 of 2021.
  • 19 December 2022: MahaRERA Member-I directed Omkar Realtors to refund the amount paid. However, the Authority allowed the builder to deduct 2% of the total consideration (as per MahaRERA Order No. 35 of 2022) and crucially denied any interest on the refunded sum.
  • 2023: Aggrieved by the absence of interest and the 2% deduction, the Mehta family filed Appeal No. AT006000000144304 of 2023 before the Maharashtra Real Estate Appellate Tribunal.
  • 23 March 2026: The appeal was heard through video conferencing.
  • 8 April 2026: In a detailed judgment authored by Member (A) Dr Rajagopal Devara (and concurred by Member (J) Shriram R. Jagtap), the Appellate Tribunal allowed the appeal. It held that under Sections 18(1)(a) and 19(4) of the RERA Act, the allottees have an “unqualified right” to full refund along with interest when the promoter fails to deliver possession. The Tribunal ruled that the delay was solely attributable to the builder and court orders, not the homebuyers. It set aside the 2% deduction and the denial of interest.

The Tribunal modified the MahaRERA order and directed Omkar Realtors to refund the full ₹7.69 crore along with interest at SBI MCLR + 2% per annum, calculated from the respective dates of payment till actual realisation. Parties are to bear their own costs.

Advocate Akash Rebello appeared for the homebuyers, while Advocate Sonali Jain represented the developer.

This order is seen as a strong reinforcement of homebuyer rights under RERA, especially in cases where projects are stalled due to the promoter’s litigation issues.

Also Read: Omkar Sells 9 Flats Worth ₹131 Crore To A Buyer

You May Also Like

Supreme Court Brings Massive Relief to Thousands of Greater Noida Homebuyers: Stalled Earth Projects to Resume Soon

“After 10 years of waiting, hope is finally here! Supreme Court orders resumption of stalled Greater Noida projects — Earth Towne, TechOne & Sapphire Court. No extra payment for homebuyers. GNIDA penal dues waived. Projects to restart from June 2026. A big win for thousands of families! 🏠⚖️”

Builder Drags Homebuyers to MahaRERA for Non-Payment, Gets Flats Cancelled & Money Forfeited

Pune developer Gera Developments dragged two homebuyers to MahaRERA for non-payment of installments. The authority cancelled both agreements but allowed the builder to forfeit only 2% instead of the demanded 10% plus charges.

Omaxe Completes Key Projects in Chandigarh & Prayagraj, Fully Repays SWAMIH Funding

Omaxe Group has completed major construction milestones in New Chandigarh and Prayagraj while fully repaying the SWAMIH Fund from internal cash flows. The achievement underscores the developer’s financial discipline, strong sales performance, and commitment to timely project execution.

MHADA Konkan Board to Conduct Lottery for 2,147 Flats, 110 Plots on February 5

The MHADA Konkan Board is set to hold a computerized lottery on February 5, 2025, for the sale of 2,147 flats and 110 plots across Thane, Raigad, and Sindhudurg. With over 24,900 applications submitted, the lottery reflects MHADA’s commitment to transparent and efficient housing allocation in Maharashtra.