The Maharashtra Real Estate Appellate Tribunal (MREAT) has condoned the delay by CCI Projects Pvt. Ltd. in filing an appeal against MahaRERA’s orders that had directed the developer to pay interest to homebuyers for delayed possession. The Tribunal held that the time spent pursuing a review application and a subsequent writ petition must be excluded from the limitation period.


Background: MahaRERA’s 2022 Order Granting Interest

MahaRERA had on 3 November 2022 ordered CCI Projects to pay interest to the allottees under Section 18 of the Real Estate (Regulation and Development) Act, citing delay in possession.
Instead of filing an appeal, the developer chose to seek a review of the order and filed a review application on 16 December 2022.


Review Dismissed Twice; High Court Intervenes

MahaRERA dismissed the review on 28 March 2023, stating it did not have the power to review its own orders.
CCI Projects then approached the Bombay High Court, which on 4 April 2024 set aside MahaRERA’s rejection and directed the authority to hear the review afresh.

Following the High Court’s direction, MahaRERA reconsidered the review and again dismissed it on 24 June 2024, upholding its original 2022 order.


Developer Learnt of Order After Checking Website

In its plea for condonation of delay, CCI Projects said it became aware of the 24 June 2024 review order only on 9 July 2024, when checking the MahaRERA website.
The order, according to the developer, was neither communicated nor pronounced.

The appeal before MREAT was filed on 19 August 2024.


Homebuyers Oppose Condonation

The allottees argued that:

  • The delay exceeded 600 days.
  • The review proceedings were “frivolous” and intended to delay compliance.
  • The appeal was time-barred under Section 44 of the RERA Act.

They sought dismissal of the appeal on the ground of limitation.


Tribunal’s Findings: Developer Acted Bonafide

Allowing the condonation plea, the Tribunal noted:

  • CCI Projects was bona fide pursuing legally available remedies — first before MahaRERA and then in the High Court.
  • The High Court’s remand validated the developer’s action of filing a review.
  • The period spent in review and writ petition proceedings must be excluded from computing delay.
  • The developer filed the appeal promptly after learning of the 24 June 2024 order.

The Tribunal concluded that the promoter had shown “sufficient cause” for the delay.


Outcome

With the delay condoned, CCI Projects’ appeal against the interest order will now be heard on merits.

Also Read: Homebuyer Loses Flat, Payment Forfeited After Ignoring MahaRERA Order to Clear Dues

You May Also Like

Pradeep Gupta Buys ₹131 Crore Luxury Flat in Lodha Sea Face, Worli

Pradeep Gupta of Anand Rathi Financial Services and his wife Priti Gupta have acquired a ₹131 crore luxury flat in Lodha Sea Face, Worli. The 40th-floor residence spans 979 sq. m. and includes seven car parks, making it one of Mumbai’s biggest luxury property transactions of 2025.

India’s Indoor Amusement Industry Hits ₹15,000 Crore; Consumer Spending Up 30–40%

India’s indoor amusement industry has reached ₹15,000 crore with consumer spending rising 30–40% since the pandemic, according to a new ANAROCK-IAAPI report. The sector, driven by malls and experiential consumption trends, is expected to grow rapidly through 2030.

NITCO Limited Sells 4 Acre Land Parcel for Rs 232 Cr to Runwal

NITCO Limited, a prominent player in the tile manufacturing sector, has announced…

📰 FSI Beyond 4! Maharashtra Cabinet Approves New Cluster Redevelopment Model for Mumbai Slums

The Maharashtra Cabinet has cleared a new cluster redevelopment scheme for Mumbai slums, allowing FSI beyond 4 to enable vertical growth and faster rehabilitation. Focused on 50+ acre clusters, the policy blends urban planning with flexible development models, potentially transforming the city’s skyline.