The Maharashtra Real Estate Appellate Tribunal (MREAT) has condoned the delay by CCI Projects Pvt. Ltd. in filing an appeal against MahaRERA’s orders that had directed the developer to pay interest to homebuyers for delayed possession. The Tribunal held that the time spent pursuing a review application and a subsequent writ petition must be excluded from the limitation period.


Background: MahaRERA’s 2022 Order Granting Interest

MahaRERA had on 3 November 2022 ordered CCI Projects to pay interest to the allottees under Section 18 of the Real Estate (Regulation and Development) Act, citing delay in possession.
Instead of filing an appeal, the developer chose to seek a review of the order and filed a review application on 16 December 2022.


Review Dismissed Twice; High Court Intervenes

MahaRERA dismissed the review on 28 March 2023, stating it did not have the power to review its own orders.
CCI Projects then approached the Bombay High Court, which on 4 April 2024 set aside MahaRERA’s rejection and directed the authority to hear the review afresh.

Following the High Court’s direction, MahaRERA reconsidered the review and again dismissed it on 24 June 2024, upholding its original 2022 order.


Developer Learnt of Order After Checking Website

In its plea for condonation of delay, CCI Projects said it became aware of the 24 June 2024 review order only on 9 July 2024, when checking the MahaRERA website.
The order, according to the developer, was neither communicated nor pronounced.

The appeal before MREAT was filed on 19 August 2024.


Homebuyers Oppose Condonation

The allottees argued that:

  • The delay exceeded 600 days.
  • The review proceedings were “frivolous” and intended to delay compliance.
  • The appeal was time-barred under Section 44 of the RERA Act.

They sought dismissal of the appeal on the ground of limitation.


Tribunal’s Findings: Developer Acted Bonafide

Allowing the condonation plea, the Tribunal noted:

  • CCI Projects was bona fide pursuing legally available remedies — first before MahaRERA and then in the High Court.
  • The High Court’s remand validated the developer’s action of filing a review.
  • The period spent in review and writ petition proceedings must be excluded from computing delay.
  • The developer filed the appeal promptly after learning of the 24 June 2024 order.

The Tribunal concluded that the promoter had shown “sufficient cause” for the delay.


Outcome

With the delay condoned, CCI Projects’ appeal against the interest order will now be heard on merits.

Also Read: Homebuyer Loses Flat, Payment Forfeited After Ignoring MahaRERA Order to Clear Dues

You May Also Like

India’s Office Market Poised for Strong Growth in 2025, Led by Engineering, BFSI, and Flex Spaces

Office leasing in India is projected to reach 65-70 million sq ft in 2025, led by engineering, BFSI, and flex spaces. Bengaluru will remain the top market, with over 20 million sq ft of demand, followed by Hyderabad and Delhi-NCR at 10-15 million sq ft each. The expansion of Global Capability Centers (GCCs) and a shift towards sustainable office spaces will further drive growth.

Maharashtra’s New GCC Push Set to Energise Office Leasing Beyond Mumbai & Pune

Maharashtra’s newly approved GCC policy targets the next wave of leasing expansion — redirecting global enterprises from Mumbai and Pune to emerging cities. With capital subsidies, added FSI, tax incentives and fast approvals, the state aims to lift GCC leasing from 15 to 25 million sq ft in five years while opening new opportunities in sectors like defense, aerospace and renewable energy.

Actor Barun Sobti buys a Luxury Residence in Mumbai’s Goregaon

Barun Sobti, best known for his roles as Arnav Singh Raizada in…

From Aug 1, Scan QR code to get Building Details

MahaRERA has come up with a notification that from August 1, a…