The Maharashtra Real Estate Appellate Tribunal (MREAT) has condoned the delay by CCI Projects Pvt. Ltd. in filing an appeal against MahaRERA’s orders that had directed the developer to pay interest to homebuyers for delayed possession. The Tribunal held that the time spent pursuing a review application and a subsequent writ petition must be excluded from the limitation period.


Background: MahaRERA’s 2022 Order Granting Interest

MahaRERA had on 3 November 2022 ordered CCI Projects to pay interest to the allottees under Section 18 of the Real Estate (Regulation and Development) Act, citing delay in possession.
Instead of filing an appeal, the developer chose to seek a review of the order and filed a review application on 16 December 2022.


Review Dismissed Twice; High Court Intervenes

MahaRERA dismissed the review on 28 March 2023, stating it did not have the power to review its own orders.
CCI Projects then approached the Bombay High Court, which on 4 April 2024 set aside MahaRERA’s rejection and directed the authority to hear the review afresh.

Following the High Court’s direction, MahaRERA reconsidered the review and again dismissed it on 24 June 2024, upholding its original 2022 order.


Developer Learnt of Order After Checking Website

In its plea for condonation of delay, CCI Projects said it became aware of the 24 June 2024 review order only on 9 July 2024, when checking the MahaRERA website.
The order, according to the developer, was neither communicated nor pronounced.

The appeal before MREAT was filed on 19 August 2024.


Homebuyers Oppose Condonation

The allottees argued that:

  • The delay exceeded 600 days.
  • The review proceedings were “frivolous” and intended to delay compliance.
  • The appeal was time-barred under Section 44 of the RERA Act.

They sought dismissal of the appeal on the ground of limitation.


Tribunal’s Findings: Developer Acted Bonafide

Allowing the condonation plea, the Tribunal noted:

  • CCI Projects was bona fide pursuing legally available remedies — first before MahaRERA and then in the High Court.
  • The High Court’s remand validated the developer’s action of filing a review.
  • The period spent in review and writ petition proceedings must be excluded from computing delay.
  • The developer filed the appeal promptly after learning of the 24 June 2024 order.

The Tribunal concluded that the promoter had shown “sufficient cause” for the delay.


Outcome

With the delay condoned, CCI Projects’ appeal against the interest order will now be heard on merits.

Also Read: Homebuyer Loses Flat, Payment Forfeited After Ignoring MahaRERA Order to Clear Dues

You May Also Like

🏗️ Realty Stocks Open Steady as Markets Digest Trump–Modi Tariff Relief; Sector Eyes Direction Through the Day

Real estate stocks opened steady as markets digested positive global cues from Trump–Modi tariff announcements. The sector is expected to trade range-bound with selective upside through the day.

Maharashtra Govt Allots Ulwe Land to Tirumala Tirupati Devasthanams for Padmavati Ammavari Temple at ₹1 per Sq m

The Maharashtra government has allotted a 14,600 sq m land parcel in Ulwe, Navi Mumbai to Tirumala Tirupati Devasthanams at a nominal rate of ₹1 per sq m for building the Sri Padmavati Ammavari Temple.

Soon You May Get Govt Aprroved Rental Home With Just a Click: MHADA’s Game-Changing Digital Portal Revealed

Soon, finding and moving into a safe, government-verified rental home in Mumbai could be as easy as ordering food online – MHADA’s new digital portal promises Aadhaar eKYC, instant police verification and digital agreements with just a click.

Bombay HC Strips Developer of Mulund Project, Society Wins Back Land

In a landmark February 16, 2026 ruling, Bombay High Court Justice Somasekhar Sundaresan directed defaulting developer Alag Property to hand over Mulund Endeavour CHS redevelopment site, appointing Court Receiver amid ₹9.77 crore dues and 5+ years displacement. A rare win empowering societies against stalled projects.