In a significant ruling reinforcing homebuyer protections under the Real Estate (Regulation and Development) Act, 2016 (RERA), the Maharashtra Real Estate Regulatory Authority (MahaRERA) has clarified that the possession date specified in an individual Agreement for Sale takes precedence over extended project completion timelines on the MahaRERA portal when calculating interest for delayed possession.

This principle was upheld in a December 23, 2025 order by MahaRERA Member II, Ravindra Deshpande, in the case of Rakesh Tailor & Anju Tailor vs. Virendra H. Doshi (successor to Dhanesh Builder). The decision rejects builders’ attempts to rely on COVID-19 extensions for escaping liability, emphasizing that buyers’ contractual rights remain absolute.

The Case Background

The complainants booked a flat in the “Siddharth Nagar Sukhvilla CHS Ltd. Phase-2” project in Goregaon West, Mumbai (MahaRERA No. P51800021400) for ₹1.71 crore. The registered Agreement for Sale, executed on December 21, 2020, explicitly promised possession by September 30, 2021.

Despite this, the Occupancy Certificate (OC) was obtained only on July 28, 2022, and possession handed over on August 1, 2022—resulting in a delay of nearly 10 months. The buyers filed a complaint seeking interest under Section 18 of RERA for the delay period.

The original promoter passed away in 2022, and the proprietorship devolved to his brother, the respondent.

Builder’s Defence: COVID Extensions and Force Majeure

The builder argued no liability for delay, citing:

  • The COVID-19 pandemic as a force majeure event under Clause 10 of the agreement.
  • MahaRERA circulars (e.g., from 2020) granting automatic 6-9 month extensions to project timelines, deeming possession dates extended accordingly.
  • The project’s revised completion date on the portal as September 30, 2022.

They claimed the construction finished by March 2022 and OC by July 2022 fell within the extended timeline.

MahaRERA’s Key Findings

MahaRERA partly allowed the complaint, directing the builder to pay interest, while rejecting the COVID defence:

  • The agreement was signed in December 2020, post the initial COVID waves, so the builder should have factored in ongoing challenges when committing to September 30, 2021.
  • MahaRERA’s COVID moratorium on interest (Order No. 14) covered only March 15, 2020 to September 14, 2020—not the post-2021 delay here.
  • Extensions applied to overall project registration dates but do not override individual possession commitments in Agreements for Sale.
  • Citing the Bombay High Court’s ruling in Neelkamal Realtors Suburban Pvt. Ltd. vs. Union of India (2017), MahaRERA held that the right to delay interest is “unconditional and absolute,” regardless of unforeseen events or portal extensions.

Interest was awarded only on ₹1.21 crore (amount paid by the agreed possession date), from October 1, 2021 to July 28, 2022, at the prescribed rate: SBI’s highest Marginal Cost of Lending Rate (MCLR) + 2% (currently around 10.70-10.80% based on latest SBI rates effective December 15, 2025).

Implications for Homebuyers and Builders

This order sends a strong message:

  • For Buyers: Scrutinize the possession date in your registered Agreement for Sale—it’s binding and protects you from unilateral extensions.
  • For Builders: Cannot hide behind portal revisions or past pandemics if the individual contract specifies an earlier date. Due diligence in committing timelines is crucial.
  • Broader Impact: Reinforces Section 18 of RERA, making delay compensation near-automatic if buyers opt to stay in the project.

With SBI’s current highest MCLR at approximately 8.80% (three-year tenor as of December 2025), the effective interest rate stands over 10%, providing substantial relief amid rising loan costs.

Conclusion

As India’s real estate sector matures under RERA, rulings like this prioritize contractual certainty and buyer rights. Homebuyers facing delays should promptly approach MahaRERA—evidence of the agreed date often seals the case.

Also Read: MahaRERA Orders Full Refund with Interest to Homebuyer for Possession Delay

You May Also Like

Positive results of notices given to developers, Information about completion of 700 projects received

As per Section 11 of the RERA Act, the project status was…

GVK’s Reddy sells Two Properties in Hyd for Rs 73.81 Cr

Two properties belonging to GVK Group’s Chairman and Founder G.V. Krishna Reddy…

India Emerges as Global Leader in Global Capability Centres

India has established itself as a premier destination for Global Capability Centres (GCCs), with over 1,800 centres occupying more than 240 million sq. ft. of Grade A office space. Recent reports indicate a projected growth to over 2,300 centres by 2026-27, underscoring India’s strategic importance in the global business ecosystem. The IT/ITeS, manufacturing, and BFSI sectors dominate this landscape, with Bengaluru leading in occupancy.

BMC Slaps Rs 103 Crore Penalty on Taj Lands End Over Property Tax Dispute

IHCL discloses fresh BMC penalty of Rs 5.51 crore on Taj Lands End, taking total property tax dispute to Rs 103 crore.